Project Start Date: Wed 10/1/97
Project Finish Date: Fri 9/29/06
| ID | Task_Name | WBS | Duration | Finish_Date | Resource_Names |
|---|---|---|---|---|---|
| 1 | User Facilities Subproject | 1 | 2252 days? | Fri 9/29/06 | |
| 2 | Tier 1 Regional Center | 1.1 | 1 day? | Wed 10/1/97 | |
| 3 | System and User Support | 1.2 | 1 day? | Wed 10/1/97 | |
| 4 | Operations and Infrastructure | 1.3 | 1 day? | Wed 10/1/97 | |
| 5 | Tier2 Regional Centers | 1.4 | 2252 days? | Fri 9/29/06 | |
| 6 | Prototype Tier2 centers | 1.4.1 | 937 days? | Mon 7/2/01 | |
| 7 | Prototype Tier2 center #1 | 1.4.1.1 | 937 days? | Mon 7/2/01 | |
| 8 | pT2 design | 1.4.1.1.1 | 1 day? | Fri 12/1/00 | |
| 9 | Design Document released | 1.4.1.1.1.1 | 1 day? | Fri 12/1/00 | |
| 10 | pT2 Equipment | 1.4.1.1.2 | 937 days? | Mon 7/2/01 | |
| 11 | Hardware Procurement & Installation | 1.4.1.1.2.1 | 166 days? | Fri 6/1/01 | |
| 12 | Farm1st Half | 1.4.1.1.2.1.1 | 45 days? | Fri 12/1/00 | |
| 13 | Vendors selected | 1.4.1.1.2.1.1.1 | 1 day? | Mon 10/2/00 | Ian Fisk |
| 14 | Procurement completed | 1.4.1.1.2.1.1.2 | 1 day? | Fri 12/1/00 | |
| 15 | Farm 2nd Half | 1.4.1.1.2.1.2 | 68 days? | Fri 6/1/01 | |
| 16 | Vendors selected | 1.4.1.1.2.1.2.1 | 1 day? | Mon 4/2/01 | Harvey Newman,Julian Bunn |
| 17 | Procurement of second Tbyte/server completed | 1.4.1.1.2.1.2.1 | 1 day? | Thu 3/1/01 | |
| 18 | Procurement of two CACR/Chicago/CERN High Performance Network nodes | 1.4.1.1.2.1.2.3 | 1 day? | Fri 3/23/01 | Harvey Newman,Julian Bunn,Ian Fisk |
| 19 | Procurement of remaining equipment completed | 1.4.1.1.2.1.2.2 | 1 day? | Fri 6/1/01 | |
| 20 | Deployment and Comissioning | 1.4.1.1.2.2 | 937 days? | Mon 7/2/01 | |
| 21 | Farm 1st Half | 1.4.1.1.2.2.1 | 864 days? | Thu 3/22/01 | |
| 22 | Installation and configuration of master and slave nodes | 1.4.1.1.2.2.1.1 | 1 day? | Wed 10/1/97 | |
| 23 | Installation and configuration of network infrastructure | 1.4.1.1.2.2.1.2 | 1 day? | Wed 10/1/97 | |
| 24 | Installation and configuration of first Tbyte disk array | 1.4.1.1.2.2.1.3 | 1 day? | Wed 10/1/97 | |
| 25 | Development of cloning scripts and procedures | 1.4.1.1.2.2.1.4 | 1 day? | Thu 3/22/01 | |
| 26 | Tested and Commissioned | 1.4.1.1.2.2.1.1 | 1 day? | Thu 2/1/01 | |
| 27 | Farm 2nd Half | 1.4.1.1.2.2.2 | 77 days? | Mon 7/2/01 | |
| 28 | Installation and configuration of second Tbyte disk array/server | 1.4.1.1.2.2.2.1 | 1 day? | Mon 3/19/01 | Julian Bunn |
| 29 | Installation and configuration of HPN network nodes | 1.4.1.1.2.2.2.2 | 1 day? | Mon 4/30/01 | |
| 30 | Shipping of one HPN node to Chicago | 1.4.1.1.2.2.2.2.1 | 1 day? | Mon 4/30/01 | |
| 31 | Tested and Commissioned | 1.4.1.1.2.2.2.1 | 1 day? | Mon 7/2/01 | |
| 32 | Hardware Maintenance | 1.4.1.1.2.3 | 1 day? | Wed 10/1/97 | |
| 33 | Benchmarking and ongoing testing | 1.4.1.1.2.1 | 1 day? | Wed 10/1/97 | Julian Bunn |
| 34 | Interface to the National Terascale Facility (NTF) | 1.4.1.1.2.4 | 1 day? | Wed 10/1/97 | |
| 35 | pT2 Software Infrastructure Framework | 1.4.1.1.3 | 863 days? | Wed 3/21/01 | |
| 36 | Installation and Deployment | 1.4.1.1.3.1 | 863 days? | Wed 3/21/01 | |
| 37 | CMS Software Environement installed | 1.4.1.1.3.1.1 | 1 day? | Wed 10/1/97 | Vladimir Litvin |
| 38 | First N fall-production events Reconstructed | 1.4.1.1.3.1.2 | 1 day? | Wed 3/21/01 | |
| 39 | Maintenance | 1.4.1.1.3.2 | 1 day? | Wed 10/1/97 | |
| 40 | Integration T1 pT2 | 1.4.1.1.4 | 1 day? | Wed 10/1/97 | |
| 41 | System Documentation | 1.4.1.1.5 | 1 day? | Mon 4/2/01 | |
| 42 | Hardware Performance Report released | 1.4.1.1.5.1 | 1 day? | Mon 4/2/01 | |
| 43 | prototype Tier2 center 2 | 1.4.1.2 | 1 day? | Wed 10/1/97 | |
| 44 | pT2 design | 1.4.1.2.1 | 1 day? | Wed 10/1/97 | |
| 45 | Design Document release | 1.4.1.2.1.1 | 1 day? | Wed 10/1/97 | |
| 46 | pT2 Equipment | 1.4.1.2.2 | 1 day? | Wed 10/1/97 | |
| 47 | Hardware Procurement & Installation | 1.4.1.2.2.1 | 1 day? | Wed 10/1/97 | |
| 48 | Farm1st Half | 1.4.1.2.2.1.1 | 1 day? | Wed 10/1/97 | |
| 49 | Vendors selected | 1.4.1.2.2.1.1.1 | 1 day? | Wed 10/1/97 | |
| 50 | Procurement completed | 1.4.1.2.2.1.1.2 | 1 day? | Wed 10/1/97 | |
| 51 | Farm 2nd Half | 1.4.1.2.2.1.2 | 1 day? | Wed 10/1/97 | |
| 52 | Vendors selected | 1.4.1.2.2.1.2.1 | 1 day? | Wed 10/1/97 | |
| 53 | Procurement completed | 1.4.1.2.2.1.2.2 | 1 day? | Wed 10/1/97 | |
| 54 | Deployment and Comissioning | 1.4.1.2.2.2 | 1 day? | Wed 10/1/97 | |
| 55 | Farm 1st Half | 1.4.1.2.2.2.1 | 1 day? | Wed 10/1/97 | |
| 56 | Tested and Commissioned | 1.4.1.2.2.2.1.1 | 1 day? | Wed 10/1/97 | |
| 57 | Farm 2nd Half | 1.4.1.2.2.2.2 | 1 day? | Wed 10/1/97 | |
| 58 | Tested and Commissioned | 1.4.1.2.2.2.2.1 | 1 day? | Wed 10/1/97 | |
| 59 | Hardware Maintenance | 1.4.1.2.2.3 | 1 day? | Wed 10/1/97 | |
| 60 | pT2 Software Infrastructure Framework | 1.4.1.2.3 | 1 day? | Wed 10/1/97 | |
| 61 | Installation and Deployment | 1.4.1.2.3.1 | 1 day? | Wed 10/1/97 | |
| 62 | CMS Software Environement installed | 1.4.1.2.3.1.1 | 1 day? | Wed 10/1/97 | |
| 63 | First N fall-production events Reconstructed | 1.4.1.2.3.1.2 | 1 day? | Wed 10/1/97 | |
| 64 | Maintenance | 1.4.1.2.3.2 | 1 day? | Wed 10/1/97 | |
| 65 | Integration T1 pT2 | 1.4.1.2.4 | 1 day? | Wed 10/1/97 | |
| 66 | System Documentation | 1.4.1.2.5 | 1 day? | Wed 10/1/97 | |
| 67 | Hardware Performance Report release | 1.4.1.2.5.1 | 1 day? | Wed 10/1/97 | |
| 68 | Tier2 related R&D | 1.4.2 | 2252 days? | Fri 9/29/06 | |
| 69 | Systems R&D | 1.4.2.1 | 1060 days? | Fri 12/28/01 | |
| 70 | Farms | 1.4.2.1.1 | 1 day? | Wed 10/1/97 | |
| 71 | Configuration and Control | 1.4.2.1.1.1 | 1 day? | Wed 10/1/97 | |
| 72 | Networks | 1.4.2.1.2 | 1 day? | Wed 10/1/97 | |
| 73 | Schedulers | 1.4.2.1.3 | 1060 days? | Fri 12/28/01 | Takako Hickey |
| 74 | Installation of scheduler on CIT and UCSD Tier2 | 1.4.2.1.3.1 | 1 day? | Fri 3/30/01 | |
| 75 | Hierarchical scheduler scheme design | 1.4.2.1.3.2 | 1 day? | Thu 5/31/01 | |
| 76 | Hierarchical scheduler deployment and tests between CIT and UCSD | 1.4.2.1.3.3 | 1 day? | Fri 6/29/01 | Takako Hickey,Vladimir Litvin |
| 77 | Integration with GDMP and Globus | 1.4.2.1.3.4 | 1 day? | Fri 9/28/01 | Takako Hickey,Asad Samar,Koen Holtman |
| 78 | Data-aware scheduling algorithm design | 1.4.2.1.3.5 | 1 day? | Wed 12/19/01 | |
| 79 | Simulation of scheduling algorithm design | 1.4.2.1.3.5.1 | 1 day? | Wed 12/19/01 | Takako Hickey,Iosif Legrand |
| 80 | Performance monitoring and continual testing | 1.4.2.1.3.7 | 1 day? | Wed 10/1/97 | |
| 81 | Implement SONN Scheduler | 1.4.2.1.3.9 | 1 day? | Fri 12/28/01 | Iosif Legrand |
| 82 | Resource Discovery and Management | 1.4.2.1.5 | 24 days? | Wed 10/31/01 | |
| 83 | Prototype network distributed service | 1.4.2.1.5.1 | 24 days? | Wed 10/31/01 | Iosif Legrand,Julian Bunn |
| 84 | Embed SONN Scheduler | 1.4.2.1.5.1.1 | 1 day? | Fri 9/28/01 | Iosif Legrand |
| 85 | Connect with local query optimization schemes | 1.4.2.1.5.1.2 | 1 day? | Wed 10/31/01 | Iosif Legrand |
| 86 | Grids R&D | 1.4.2.2 | 2252 days? | Fri 9/29/06 | |
| 87 | Distributed Production File Service (PPDG Deliverables) | 1.4.2.2.11 | 1 day? | Wed 10/1/97 | |
| 88 | Global namespace definition for files | 1.4.2.2.11.1 | 1 day? | Wed 10/1/97 | |
| 89 | Job Control Language and its User Interface | 1.4.2.2.11.2 | 1 day? | Wed 10/1/97 | |
| 90 | File Management (caching, staging) | 1.4.2.2.11.3 | 1 day? | Wed 10/1/97 | |
| 91 | HRM Integration with HPSS, Enstore, Castor | 1.4.2.2.11.4 | 1 day? | Wed 10/1/97 | |
| 92 | Globus Metadata Catalog | 1.4.2.2.11.5 | 1 day? | Wed 10/1/97 | |
| 93 | System capabilities matchmaking and priorities | 1.4.2.2.11.6 | 1 day? | Wed 10/1/97 | |
| 94 | Monitoring tools for data location, task progress, completion estimates | 1.4.2.2.11.7 | 1 day? | Wed 10/1/97 | |
| 95 | Develop Digital Signature system for dataset provenance | 1.4.2.2.11.8 | 1 day? | Wed 10/1/97 | |
| 96 | Transport and delivery of Object Collections | 1.4.2.2.11.9 | 1 day? | Wed 10/1/97 | |
| 97 | Synchronize metadata catalogues with Globus replica catalog | 1.4.2.2.11.10 | 1 day? | Wed 10/1/97 | |
| 98 | Distributed Analysis Service (PPDG Deliverables) | 1.4.2.2.13 | 1 day? | Wed 10/1/97 | |
| 99 | Tools for handling analysis files | 1.4.2.2.13.1 | 1 day? | Wed 10/1/97 | |
| 100 | Tools to interrogate systems status | 1.4.2.2.13.2 | 1 day? | Wed 10/1/97 | |
| 101 | Tools for monitoring costs and request redirection | 1.4.2.2.13.3 | 1 day? | Wed 10/1/97 | |
| 102 | Tools for handling file replicas | 1.4.2.2.13.4 | 1 day? | Wed 10/1/97 | |
| 103 | Integration of Tools into the CMS UAE | 1.4.2.2.13.5 | 1 day? | Wed 10/1/97 | |
| 104 | Object-Collection Access (PPDG Deliverables) | 1.4.2.2.15 | 1 day? | Wed 10/1/97 | |
| 105 | Object collection extraction, transport and delivery | 1.4.2.2.15.1 | 1 day? | Wed 10/1/97 | |
| 106 | Integratiion of Object collections with ODBMS | 1.4.2.2.15.2 | 1 day? | Wed 10/1/97 | |
| 107 | Concurrency support for Metadata Catalog | 1.4.2.2.15.3 | 1 day? | Wed 10/1/97 | |
| 108 | GDMP Productizing | 1.4.2.2.2 | 154 days? | Fri 11/30/01 | Asad Samar |
| 109 | GDMP Configured and Release 1 | 1.4.2.2.2.1 | 1 day? | Tue 5/1/01 | |
| 110 | GDMP Configured and Release 2 | 1.4.2.2.2.2 | 154 days? | Fri 11/30/01 | |
| 111 | GDMP Stability and Scalability | 1.4.2.2.3 | 264 days? | Fri 3/29/02 | Asad Samar |
| 112 | 100GB milestone | 1.4.2.2.3.1 | 1 day? | Wed 3/14/01 | Asad Samar |
| 113 | 1TB milestone | 1.4.2.2.3.2 | 88 days? | Fri 11/30/01 | Asad Samar |
| 114 | Successful tests with HPSS integration | 1.4.2.2.3.3 | 1 day? | Fri 8/31/01 | Asad Samar |
| 115 | GDMP integration with Globus Replica Catalog | 1.4.2.2.3.4 | 1 day? | Fri 8/31/01 | Asad Samar |
| 116 | GDMP integration with Globus Replica Manager | 1.4.2.2.3.5 | 1 day? | Fri 3/29/02 | Asad Samar |
| 117 | GDMP integration with Network Weather Service | 1.4.2.2.3.6 | 1 day? | Fri 3/29/02 | Asad Samar |
| 118 | CMS Grid Requirements and Modelling Documentation | 1.4.2.2.5 | 915 days? | Thu 5/31/01 | Koen Holtman |
| 119 | 2006 grid workload modeling | 1.4.2.2.5.3 | 1 day? | Thu 5/31/01 | Koen Holtman |
| 120 | Long term requirements | 1.4.2.2.5.1 | 1 day? | Wed 10/1/97 | Koen Holtman,Harvey Newman |
| 121 | Object-level Cataloguing and Replication System | 1.4.2.2.6 | 1024 days? | Wed 10/31/01 | Koen Holtman |
| 122 | Demonstrate scalability to at least 5 sites | 1.4.2.2.6.1 | 1 day? | Wed 10/31/01 | Koen Holtman |
| 123 | Demonstrate scalability to > 5.10^6 objects | 1.4.2.2.6.2 | 1 day? | Wed 10/1/97 | Koen Holtman |
| 124 | Production Frameworks | 1.4.2.2.8 | 1 day? | Wed 10/1/97 | |
| 125 | Query Optimisation studies | 1.4.2.2.10 | 1 day? | Fri 9/29/06 | Iosif Legrand,Kurt Stockinger,Julian Bunn |
| 126 | Interactive Analysis | 1.4.2.4 | 1059 days? | Wed 12/19/01 | |
| 127 | Create Tag datasets for analysis tool evaluations | 1.4.2.4.4 | 1 day? | Thu 5/31/01 | Koen Holtman,Conrad Steenberg |
| 128 | Performance analysis of Tag storage schemes | 1.4.2.4.7 | 1 day? | Tue 6/12/01 | Kurt Stockinger |
| 129 | Distributed Analysis Prototype | 1.4.2.4.5 | 1059 days? | Wed 12/19/01 | |
| 130 | JAS server-side Tag/HTL Data Interface Module Prototype | 1.4.2.4.5.1 | 1 day? | Tue 6/12/01 | Conrad Steenberg,Kurt Stockinger |
| 131 | JAS server DIM release | 1.4.2.4.5.2 | 1 day? | Fri 6/29/01 | |
| 132 | Java GUI for Tag/HTML Analysis | 1.4.2.4.5.3 | 1 day? | Fri 7/27/01 | |
| 133 | Scalability testing of the JAS-based Analysis system | 1.4.2.4.5.4 | 1 day? | Wed 10/1/97 | |
| 134 | Investigation of data transport technologies | 1.4.2.4.5.5 | 1 day? | Wed 12/19/01 | |
| 135 | C++ TagHTLDIM | 1.4.2.4.5.5.1 | 1 day? | Wed 12/19/01 | |
| 136 | Tier2/TierN Models and Simulations | 1.4.6 | 46 days? | Fri 8/31/01 | |
| 137 | Simulation of data access strategies | 1.4.6.1 | 1 day? | Fri 6/29/01 | |
| 138 | Parameter Collection Tool | 1.4.6.2 | 1 day? | Tue 7/31/01 | |
| 139 | SONN Scheduler Simulation | 1.4.6.3 | 1 day? | Fri 8/31/01 | Iosif Legrand |
| 140 | Add data-awareness | 1.4.6.3.1 | 1 day? | Fri 8/31/01 | Iosif Legrand |
| 141 | Evaluation | 1.4.6.3.2 | 1 day? | Fri 8/31/01 | Iosif Legrand |
| 142 | Tier2 Production Operations | 1.4.3 | 981 days? | Fri 8/31/01 | |
| 143 | Distributed Production scheme | 1.4.3.4 | 117 days? | Fri 8/31/01 | |
| 144 | White paper | 1.4.3.4.1 | 1 day? | Fri 3/23/01 | |
| 145 | Create system and test with CMSIM | 1.4.3.4.2 | 45 days? | Thu 5/31/01 | |
| 146 | Tests with ORCA | 1.4.3.4.3 | 66 days? | Fri 8/31/01 | |
| 147 | Simulation | 1.4.3.1 | 45 days? | Fri 6/1/01 | |
| 148 | Setup of full scale CMSIM Production | 1.4.3.1.1 | 1 day? | Thu 5/31/01 | Vladimir Litvin |
| 149 | Setup of full scale ORCA Production | 1.4.3.1.2 | 1 day? | Thu 5/31/01 | Vladimir Litvin |
| 150 | Full scale production runs | 1.4.3.1.3 | 44 days? | Thu 5/31/01 | Vladimir Litvin |
| 151 | Start of Simulation/Reconstruction of M events fom CMS Fall2000 Production delivered | 1.4.3.1.1 | 1 day? | Fri 6/1/01 | |
| 152 | Reprocessing | 1.4.3.2 | 1 day? | Wed 10/1/97 | |
| 153 | Tier2 Related Production | 1.4.1 | 88 days? | Fri 6/29/01 | |
| 154 | ORCA Production on Los Lobos cluster | 1.4.1.1 | 1 day? | Fri 4/27/01 | Vladimir Litvin |
| 155 | Higgs Datasample generation on CACR Exemplar | 1.4.1.2 | 87 days? | Fri 6/29/01 | Vladimir Litvin |
| 156 | Distributed CMSIM tests for NTF | 1.4.1.3 | 22 days? | Tue 5/1/01 | Vladimir Litvin |
| 157 | CMSIM Production on UW-Madison Condor | 1.4.1.4 | 45 days? | Fri 6/1/01 | Vladimir Litvin |
| 158 | CMSIM/ORCA Production on ANL Cluster | 1.4.1.5 | 24 days? | Thu 5/31/01 | Vladimir Litvin |
| 159 | Tier2 centers | 1.4.4 | 1500 days | Fri 9/26/03 | |
| 160 | Tier 2 Center 1 | 1.4.4.1 | 1500 days | Fri 9/26/03 | |
| 161 | 1.4.1.1 T2 Design | 1.4.4.1.1 | 1 day | Wed 10/1/97 | |
| 162 | 1.4.1.2 T2 Equipment | 1.4.4.1.2 | 1500 days | Fri 9/26/03 | |
| 163 | 1.4.1.2.1 Hardware Procurement & Installation | 1.4.4.1.2.1 | 1 day | Wed 10/1/97 | |
| 164 | 1.4.1.2.2 Commissioning | 1.4.4.1.2.2 | 1 day | Wed 10/1/97 | |
| 165 | 1.4.1.2.3 Hardware Maintenance | 1.4.4.1.2.3 | 1500 days | Fri 9/26/03 | |
| 166 | 1.4.1.3 T2 Software Infrastructure Framework | 1.4.4.1.3 | 1 day | Wed 10/1/97 | |
| 167 | 1.4.1.3.1 Installation and Deployment | 1.4.4.1.3.1 | 1 day | Wed 10/1/97 | |
| 168 | 1.4.1.3.2 Maintenance | 1.4.4.1.3.2 | 1 day | Wed 10/1/97 | |
| 169 | 1.4.1.4 Integration with T1/T2 | 1.4.4.1.4 | 1 day | Wed 10/1/97 | |
| 170 | 1.4.1.5 System Documentation | 1.4.4.1.5 | 1 day | Wed 10/1/97 | |
| 171 | Tier 2 Center 2 | 1.4.4.2 | 1500 days | Fri 9/26/03 | |
| 172 | 1.4.2.1 T2 Design | 1.4.4.2.1 | 1 day | Wed 10/1/97 | |
| 173 | 1.4.2.2 T2 Equipment | 1.4.4.2.2 | 1500 days | Fri 9/26/03 | |
| 174 | 1.4.2.2.1 Hardware Procurement & Installation | 1.4.4.2.2.1 | 1 day | Wed 10/1/97 | |
| 175 | 1.4.2.2.2 Commissioning | 1.4.4.2.2.2 | 1 day | Wed 10/1/97 | |
| 176 | 1.4.2.2.3 Hardware Maintenance | 1.4.4.2.2.3 | 1500 days | Fri 9/26/03 | |
| 177 | 1.4.2.3 T2 Software Infrastructure Framework | 1.4.4.2.3 | 1 day | Wed 10/1/97 | |
| 178 | 1.4.2.3.1 Installation and Deployment | 1.4.4.2.3.1 | 1 day | Wed 10/1/97 | |
| 179 | 1.4.2.3.2 Maintenance | 1.4.4.2.3.2 | 1 day | Wed 10/1/97 | |
| 180 | 1.4.2.4 Integration with T1/T2 | 1.4.4.2.4 | 1 day | Wed 10/1/97 | |
| 181 | 1.4.2.5 System Documentation | 1.4.4.2.5 | 1 day | Wed 10/1/97 | |
| 182 | Tier 2 Center 3 | 1.4.4.3 | 1000 days | Thu 9/27/01 | |
| 183 | 1.4.2.1 T2 Design | 1.4.4.3.1 | 1 day | Wed 10/1/97 | |
| 184 | 1.4.2.2 T2 Equipment | 1.4.4.3.2 | 1000 days | Thu 9/27/01 | |
| 185 | 1.4.2.2.1 Hardware Procurement & Installation | 1.4.4.3.2.1 | 1 day | Wed 10/1/97 | |
| 186 | 1.4.2.2.2 Commissioning | 1.4.4.3.2.2 | 1 day | Wed 10/1/97 | |
| 187 | 1.4.2.2.3 Hardware Maintenance | 1.4.4.3.2.3 | 1000 days | Thu 9/27/01 | |
| 188 | 1.4.2.3 T2 Software Infrastructure Framework | 1.4.4.3.3 | 1 day | Wed 10/1/97 | |
| 189 | 1.4.2.3.1 Installation and Deployment | 1.4.4.3.3.1 | 1 day | Wed 10/1/97 | |
| 190 | 1.4.2.3.2 Maintenance | 1.4.4.3.3.2 | 1 day | Wed 10/1/97 | |
| 191 | 1.4.2.4 Integration with T1/T2 | 1.4.4.3.4 | 1 day | Wed 10/1/97 | |
| 192 | 1.4.2.5 System Documentation | 1.4.4.3.5 | 1 day | Wed 10/1/97 | |
| 193 | Tier 2 Center 4 | 1.4.4.4 | 500 days | Thu 9/30/99 | |
| 194 | 1.4.2.1 T2 Design | 1.4.4.4.1 | 1 day | Wed 10/1/97 | |
| 195 | 1.4.2.2 T2 Equipment | 1.4.4.4.2 | 500 days | Thu 9/30/99 | |
| 196 | 1.4.2.2.1 Hardware Procurement & Installation | 1.4.4.4.2.1 | 1 day | Wed 10/1/97 | |
| 197 | 1.4.2.2.2 Commissioning | 1.4.4.4.2.2 | 1 day | Wed 10/1/97 | |
| 198 | 1.4.2.2.3 Hardware Maintenance | 1.4.4.4.2.3 | 500 days | Thu 9/30/99 | |
| 199 | 1.4.2.3 T2 Software Infrastructure Framework | 1.4.4.4.3 | 1 day | Wed 10/1/97 | |
| 200 | 1.4.2.3.1 Installation and Deployment | 1.4.4.4.3.1 | 1 day | Wed 10/1/97 | |
| 201 | 1.4.2.3.2 Maintenance | 1.4.4.4.3.2 | 1 day | Wed 10/1/97 | |
| 202 | 1.4.2.4 Integration with T1/T2 | 1.4.4.4.4 | 1 day | Wed 10/1/97 | |
| 203 | 1.4.2.5 System Documentation | 1.4.4.4.5 | 1 day | Wed 10/1/97 | |
| 204 | Tier 2 Center 5 | 1.4.4.5 | 250 days | Wed 9/30/98 | |
| 205 | 1.4.2.1 T2 Design | 1.4.4.5.1 | 1 day | Wed 10/1/97 | |
| 206 | 1.4.2.2 T2 Equipment | 1.4.4.5.2 | 250 days | Wed 9/30/98 | |
| 207 | 1.4.2.2.1 Hardware Procurement & Installation | 1.4.4.5.2.1 | 1 day | Wed 10/1/97 | |
| 208 | 1.4.2.2.2 Commissioning | 1.4.4.5.2.2 | 1 day | Wed 10/1/97 | |
| 209 | 1.4.2.2.3 Hardware Maintenance | 1.4.4.5.2.3 | 250 days | Wed 9/30/98 | |
| 210 | 1.4.2.3 T2 Software Infrastructure Framework | 1.4.4.5.3 | 1 day | Wed 10/1/97 | |
| 211 | 1.4.2.3.1 Installation and Deployment | 1.4.4.5.3.1 | 1 day | Wed 10/1/97 | |
| 212 | 1.4.2.3.2 Maintenance | 1.4.4.5.3.2 | 1 day | Wed 10/1/97 | |
| 213 | 1.4.2.4 Integration with T1/T2 | 1.4.4.5.4 | 1 day | Wed 10/1/97 | |
| 214 | 1.4.2.5 System Documentation | 1.4.4.5.5 | 1 day | Wed 10/1/97 |