Project Start Date: Thu 01-01-98
Project Finish Date: Tue 02-01-07
ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
---|---|---|---|---|---|---|
1 | Project Management | 434 wks | Thu 01-01-98 | Mon 01-01-07 | 0% | |
2 | Overall Project Management | 434 wks | Thu 01-01-98 | Mon 01-01-07 | Project Manager | 0% |
3 | Resource Management | 434 wks | Thu 01-01-98 | Mon 01-01-07 | Resource Manager[75%] | 0% |
4 | Computing co-ordination | 434 wks | Thu 01-01-98 | Mon 01-01-07 | Computing Manager | 0% |
5 | Computing | 433.8 wks | Thu 01-01-98 | Fri 29-12-06 | 0% | |
6 | Central Systems | 433.8 wks | Thu 01-01-98 | Fri 29-12-06 | 0% | |
7 | Central systems Phase I | 238 wks | Thu 01-01-98 | Fri 13-12-02 | 0% | |
8 | Central systems: Functional prototype | 0 wks | Sun 15-12-02 | Sun 15-12-02 | 0% | |
9 | Central systems Phase II | 48 wks | Mon 16-12-02 | Fri 12-12-03 | 0% | |
10 | Central systems: turn on initial systems | 0 wks | Mon 15-12-03 | Mon 15-12-03 | 0% | |
11 | Central systems Phase III | 71.6 wks | Mon 15-12-03 | Fri 10-06-05 | 0% | |
12 | Central systems: Fully operational systems | 0 wks | Wed 15-06-05 | Wed 15-06-05 | 0% | |
13 | Central systems Phase IV | 75.8 wks | Wed 15-06-05 | Fri 29-12-06 | 0% | |
14 | Regional centres | 409.8 wks | Wed 01-07-98 | Fri 29-12-06 | 0% | |
15 | Evaluation of Regional Centres | 93.4 wks | Wed 01-07-98 | Fri 09-06-00 | 0% | |
16 | Identify initial candidates | 0 wks | Thu 15-06-00 | Thu 15-06-00 | 0% | |
17 | Develop functional Regional Centres | 120 wks | Thu 15-06-00 | Fri 13-12-02 | 0% | |
18 | "Turn on" functional Regional Centres | 0 wks | Mon 16-12-02 | Mon 16-12-02 | 0% | |
19 | Develop operational Regional Centres | 120 wks | Mon 16-12-02 | Tue 14-06-05 | 0% | |
20 | Fully operational Regional Centres | 0 wks | Wed 15-06-05 | Wed 15-06-05 | 0% | |
21 | Operation of Regional Centres | 75.8 wks | Wed 15-06-05 | Fri 29-12-06 | 0% | |
22 | Software | 434.2 wks | Thu 01-01-98 | Tue 02-01-07 | 0% | |
23 | CMSIM | 166 wks | Thu 01-01-98 | Thu 14-06-01 | 0% | |
24 | CMSIM development | 22 wks | Thu 01-01-98 | Fri 12-06-98 | CMSIM Coordinator | 0% |
25 | Cessation of new development | 0 wks | Mon 15-06-98 | Mon 15-06-98 | 0% | |
26 | CMSIM maintenance | 144 wks | Mon 15-06-98 | Thu 14-06-01 | CMSIM Coordinator[25%] | 0% |
27 | Software Process | 433.8 wks | Thu 01-01-98 | Fri 29-12-06 | 0% | |
28 | SP Phase I: Development of proof of concept | 56 wks | Thu 01-01-98 | Fri 26-02-99 | SW Process Coordinator | 0% |
29 | SP Phase II: Development of functional prototype | 60 wks | Mon 01-03-99 | Fri 26-05-00 | SW Process Coordinator,Quality Assurer | 0% |
30 | SP Phase III: Development of fully functional software | 120 wks | Thu 01-06-00 | Thu 28-11-02 | SW Process Coordinator,SW Process Toolsmith,Quality Assurer | 0% |
31 | SP Phase IV: Development of production software | 197.8 wks | Mon 02-12-02 | Fri 29-12-06 | SW Process Coordinator,SW Process Toolsmith,Quality Assurer | 0% |
32 | Software Support | 433.8 wks | Thu 01-01-98 | Fri 29-12-06 | 0% | |
33 | SS Phase I: Development of proof of concept | 56 wks | Thu 01-01-98 | Fri 26-02-99 | Librarian 1,SS Toolsmith,Documentor 1 | 0% |
34 | SS Phase II: Development of functional prototype | 60 wks | Mon 01-03-99 | Fri 26-05-00 | Librarian 1,Documentor 1,SS Toolsmith | 0% |
35 | SS Phase III: Development of fully functional software | 120 wks | Thu 01-06-00 | Thu 28-11-02 | Librarian 1,Documentor 1,SS Toolsmith | 0% |
36 | SS Phase IV: Development of production software | 197.8 wks | Mon 02-12-02 | Fri 29-12-06 | Librarian 1,Documentor 1,SS Toolsmith,Librarian 2,Documentor 2 | 0% |
37 | Information Systems | 433.8 wks | Thu 01-01-98 | Fri 29-12-06 | 0% | |
38 | WWW Phase 1 | 239 wks | Thu 01-01-98 | Fri 20-12-02 | WWW Coordinator | 0% |
39 | WWW Phase 2 | 194.8 wks | Mon 23-12-02 | Fri 29-12-06 | WWW Coordinator,WWW Administrator | 0% |
40 | Collaboration Database Phase 1 | 239 wks | Thu 01-01-98 | Fri 20-12-02 | Collaboration database programmer[25%] | 0% |
41 | Collaboration Database Phase 2 | 194.8 wks | Mon 23-12-02 | Fri 29-12-06 | Collaboration database programmer[50%] | 0% |
42 | CARF | 434.2 wks | Thu 01-01-98 | Tue 02-01-07 | 0% | |
43 | CARF development of concept | 22 wks | Thu 01-01-98 | Fri 12-06-98 | 0% | |
44 | CARF development of concept | 22 wks | Thu 01-01-98 | Fri 12-06-98 | Chief Architect | 0% |
45 | Proof of concept | 0 wks | Mon 15-06-98 | Mon 15-06-98 | 0% | |
46 | CARF prototyping | 71.4 wks | Tue 16-06-98 | Fri 10-12-99 | 0% | |
47 | CARF prototyping 1 | 71.4 wks | Tue 16-06-98 | Fri 10-12-99 | Chief Architect,Architect | 0% |
48 | Functional prototype | 0 wks | Wed 15-12-99 | Wed 15-12-99 | 0% | |
49 | CARF development | 92 wks | Mon 10-01-00 | Fri 07-12-01 | 0% | |
50 | CARF development 1 | 92 wks | Mon 10-01-00 | Fri 07-12-01 | Chief Architect,Architect | 0% |
51 | Fully functional software | 0 wks | Sat 15-12-01 | Sat 15-12-01 | 0% | |
52 | CARF productisation | 96 wks | Mon 17-12-01 | Fri 12-12-03 | 0% | |
53 | CARF productisation 1 | 96 wks | Mon 17-12-01 | Fri 12-12-03 | Chief Architect,Architect,CARF SW Engineer | 0% |
54 | Production software | 0 wks | Tue 16-12-03 | Tue 16-12-03 | 0% | |
55 | CARF production | 148 wks | Tue 16-12-03 | Tue 02-01-07 | 0% | |
56 | CARF production 1 | 148 wks | Tue 16-12-03 | Tue 02-01-07 | Chief Architect,Architect,CARF SW Engineer | 0% |
57 | Event Generators | 366 wks | Tue 01-06-99 | Mon 01-01-07 | 0% | |
58 | Implementation of Event Generator "Framework" | 25.6 wks | Tue 01-06-99 | Fri 10-12-99 | EG Coordinator | 0% |
59 | Functional system | 0 wks | Wed 15-12-99 | Wed 15-12-99 | 0% | |
60 | Maintenance of "Framework" | 340 wks | Wed 15-12-99 | Mon 01-01-07 | EG Coordinator[20%] | 0% |
61 | New generators, standard samples | 340 wks | Wed 15-12-99 | Mon 01-01-07 | EG Coordinator[80%] | 0% |
62 | Detector Description | 413.8 wks | Mon 01-06-98 | Fri 29-12-06 | 0% | |
63 | Phase I | 44 wks | Mon 01-06-98 | Wed 28-04-99 | Magnetic field programmer[25%] | 0% |
64 | Phase II | 32.01 wks | Mon 03-05-99 | Sat 01-01-00 | Magnetic field programmer[25%],DD Coordinator[50%],DD SW Engineer | 0% |
65 | Phase III | 69.19 wks | Sat 01-01-00 | Fri 08-06-01 | Magnetic field programmer[25%],DD Coordinator,DD SW Engineer | 0% |
66 | Phase IV | 268.6 wks | Mon 11-06-01 | Fri 29-12-06 | Magnetic field programmer[25%],DD Coordinator,DD SW Engineer | 0% |
67 | Fast Simulation | 365.8 wks | Tue 01-06-99 | Fri 29-12-06 | 0% | |
68 | Fast Sim: Development of concept | 26 wks | Tue 01-06-99 | Tue 14-12-99 | Fast Sim. Coordinator[50%] | 0% |
69 | Fast Sim: Proof of concept | 0 wks | Wed 15-12-99 | Wed 15-12-99 | 0% | |
70 | Fast Sim: Development of functional prototype | 48 wks | Wed 15-12-99 | Thu 14-12-00 | Fast Sim. Coordinator,Fast Sim. SW Engineer | 0% |
71 | Fast Sim: Functional prototype | 0 wks | Fri 15-12-00 | Fri 15-12-00 | 0% | |
72 | Fast Sim: Development of fully functional software | 71 wks | Fri 15-12-00 | Fri 07-06-02 | Fast Sim. Coordinator,Fast Sim. SW Engineer | 0% |
73 | Fast Sim: Fully functional software | 0 wks | Fri 14-06-02 | Fri 14-06-02 | 0% | |
74 | Fast Sim: Development of production software | 96 wks | Fri 14-06-02 | Fri 11-06-04 | Fast Sim. Coordinator,Fast Sim. SW Engineer | 0% |
75 | Fast Sim: Production software | 0 wks | Tue 15-06-04 | Tue 15-06-04 | 0% | |
76 | Fast Sim: production and development | 123.8 wks | Tue 15-06-04 | Fri 29-12-06 | Fast Sim. Coordinator,Fast Sim. SW Engineer | 0% |
77 | OSCAR | 433.8 wks | Thu 01-01-98 | Fri 29-12-06 | 0% | |
78 | OSCAR Development of concept | 22 wks | Thu 01-01-98 | Fri 12-06-98 | OSCAR Coordinator[50%] | 0% |
79 | OSCAR Proof of concept | 0 wks | Mon 15-06-98 | Mon 15-06-98 | 0% | |
80 | OSCAR Prototyping | 71.6 wks | Mon 15-06-98 | Fri 10-12-99 | OSCAR Coordinator,OSCAR SW Engineer | 0% |
81 | OSCAR Functional prototype | 0 wks | Wed 15-12-99 | Wed 15-12-99 | 0% | |
82 | OSCAR Development | 71.2 wks | Wed 15-12-99 | Fri 08-06-01 | OSCAR Coordinator,OSCAR SW Engineer | 0% |
83 | OSCAR Fully functional software | 0 wks | Fri 15-06-01 | Fri 15-06-01 | 0% | |
84 | OSCAR Production | 120 wks | Fri 15-06-01 | Fri 12-12-03 | OSCAR Coordinator,OSCAR SW Engineer | 0% |
85 | OSCAR Production software | 0 wks | Mon 15-12-03 | Mon 15-12-03 | 0% | |
86 | OSCAR Production | 147.8 wks | Mon 15-12-03 | Fri 29-12-06 | OSCAR Coordinator,OSCAR SW Engineer | 0% |
87 | ORCA Detector Reconstruction | 410 wks | Wed 01-07-98 | Mon 01-01-07 | 0% | |
88 | Development of concept | 22 wks | Wed 01-07-98 | Mon 14-12-98 | 0% | |
89 | Development of ORCA version 1 | 22 wks | Wed 01-07-98 | Mon 14-12-98 | Programmer: Tracker,ORCA Coordinator | 0% |
90 | Proof of concept | 0 wks | Tue 15-12-98 | Tue 15-12-98 | 0% | |
91 | Prototyping | 44.8 wks | Tue 15-12-98 | Fri 19-11-99 | 0% | |
92 | Develop ORCA version 2 | 16 wks | Tue 15-12-98 | Wed 14-04-99 | ORCA Coordinator,Programmer: Tracker,ORCA SW Engineer | 0% |
93 | ORCA 2 release | 0 wks | Thu 15-04-99 | Thu 15-04-99 | 0% | |
94 | Develop ORCA version 3 | 16 wks | Thu 15-04-99 | Fri 13-08-99 | ORCA Coordinator,Programmer: Tracker,ORCA SW Engineer | 0% |
95 | ORCA 3 release | 0 wks | Fri 20-08-99 | Fri 20-08-99 | 0% | |
96 | Develop ORCA version 4 | 12 wks | Fri 20-08-99 | Thu 18-11-99 | ORCA Coordinator,Programmer: Tracker,ORCA SW Engineer | 0% |
97 | ORCA 4 release | 0 wks | Fri 19-11-99 | Fri 19-11-99 | 0% | |
98 | Functional prototype | 0 wks | Wed 15-12-99 | Wed 15-12-99 | 0% | |
99 | Development | 120 wks | Wed 15-12-99 | Fri 14-06-02 | 0% | |
100 | Development 1 | 120 wks | Wed 15-12-99 | Fri 14-06-02 | Programmer: Tracker,ORCA Coordinator,ORCA SW Engineer | 0% |
101 | Fully functional software | 0 wks | Mon 17-06-02 | Mon 17-06-02 | 0% | |
102 | Productisation | 96 wks | Mon 17-06-02 | Mon 14-06-04 | 0% | |
103 | Productisation 1 | 96 wks | Mon 17-06-02 | Mon 14-06-04 | Programmer: Tracker,ORCA Coordinator,ORCA SW Engineer | 0% |
104 | Production software | 0 wks | Tue 15-06-04 | Tue 15-06-04 | 0% | |
105 | ORCA production | 124 wks | Tue 15-06-04 | Mon 01-01-07 | 0% | |
106 | Production 1 | 124 wks | Tue 15-06-04 | Mon 01-01-07 | Programmer: Tracker,ORCA Coordinator,ORCA SW Engineer | 0% |
107 | Physics Object Reconstruction and HLT | 385.4 wks | Tue 05-01-99 | Fri 29-12-06 | 0% | |
108 | POR_HLT Development of concept | 9.6 wks | Tue 05-01-99 | Fri 12-03-99 | POR/HTL Coordinator[50%] | 0% |
109 | POR_HLT Proof of concept | 0 wks | Mon 15-03-99 | Mon 15-03-99 | 0% | |
110 | POR_HLT Prototyping | 59.4 wks | Mon 15-03-99 | Fri 09-06-00 | POR/HTL Coordinator | 0% |
111 | POR_HLT Functional prototype | 0 wks | Thu 15-06-00 | Thu 15-06-00 | 0% | |
112 | POR_HLT Development | 120 wks | Thu 15-06-00 | Fri 13-12-02 | POR/HTL Coordinator,POR/HLT SW Engineer | 0% |
113 | POR_HLT Fully functional software | 0 wks | Mon 16-12-02 | Mon 16-12-02 | 0% | |
114 | POR_HLT Production | 95.6 wks | Mon 16-12-02 | Fri 10-12-04 | POR/HTL Coordinator,POR/HLT SW Engineer | 0% |
115 | POR_HLT Production software | 0 wks | Wed 15-12-04 | Wed 15-12-04 | 0% | |
116 | POR_HLT Production | 99.8 wks | Wed 15-12-04 | Fri 29-12-06 | POR/HTL Coordinator,POR/HLT SW Engineer | 0% |
117 | User Analysis Environment | 433.6 wks | Mon 05-01-98 | Mon 01-01-07 | 0% | |
118 | UAE Coordination | 374 wks | Thu 01-04-99 | Mon 01-01-07 | 0% | |
119 | UAE Coordination 1 | 36 wks | Thu 01-04-99 | Fri 31-12-99 | UAE Coordinator[25%] | 0% |
120 | UAE Coordination 2 | 118 wks | Sat 01-01-00 | Fri 14-06-02 | UAE Coordinator[50%] | 0% |
121 | UAE Coordination 3 | 220 wks | Mon 17-06-02 | Mon 01-01-07 | UAE Coordinator[50%] | 0% |
122 | CMSCAN Event Visualisation | 433.4 wks | Mon 05-01-98 | Fri 29-12-06 | 0% | |
123 | CMSCAN Development of concept | 43.6 wks | Mon 05-01-98 | Fri 27-11-98 | 0% | |
124 | CMSCAN prototyping with CMSIM | 28.6 wks | Mon 05-01-98 | Fri 07-08-98 | 0% | |
125 | Standalone OpenGL/OpenInventor prototype | 8 wks | Mon 05-01-98 | Tue 03-03-98 | Physicist programmer 1[25%] | 0% |
126 | Create basic SO classes and deploy HEPVis | 10 wks | Wed 04-03-98 | Mon 18-05-98 | Physicist programmer 1[25%] | 0% |
127 | X11/MOTIF interactive GUI | 6 wks | Wed 04-03-98 | Thu 16-04-98 | UAE Coordinator[50%],Physicist programmer 1[25%] | 0% |
128 | Interface with CMSIM (prototype display) | 4 wks | Tue 19-05-98 | Tue 16-06-98 | UAE Coordinator[50%],Physicist programmer 1[25%] | 0% |
129 | GEANT3 interface and SO classes for G3 shapes | 6.6 wks | Wed 17-06-98 | Fri 07-08-98 | UAE Coordinator[50%],Physicist programmer 1[25%],Physicist programmer 2[25%] | 0% |
130 | Prototype CMSCAN display using CMSIM | 0 wks | Sat 15-08-98 | Sat 15-08-98 | 0% | |
131 | CMSCAN prototyping with ORCA | 14 wks | Mon 17-08-98 | Fri 27-11-98 | 0% | |
132 | Integration with CARF, ORCA, SRT | 6 wks | Mon 17-08-98 | Mon 28-09-98 | UAE Coordinator[50%] | 0% |
133 | Display of some CMS detector elements | 2 wks | Thu 01-10-98 | Wed 14-10-98 | UAE Coordinator[50%] | 0% |
134 | Display of some ORCA reconstructed objects | 3 wks | Thu 15-10-98 | Fri 06-11-98 | UAE Coordinator[50%] | 0% |
135 | Integration and release with ORCA version 1 | 3 wks | Mon 09-11-98 | Fri 27-11-98 | UAE Coordinator[50%] | 0% |
136 | CMSCAN proof of concept | 0 wks | Mon 14-12-98 | Mon 14-12-98 | 0% | |
137 | CMSCAN Functional protoyping within ORCA | 71.6 wks | Mon 14-12-98 | Fri 09-06-00 | 0% | |
138 | CMSCAN event display manager | 2 wks | Mon 14-12-98 | Mon 28-12-98 | UAE Coordinator[50%],Visualisation SW Engineer | 0% |
139 | CMSCAN management of graphics tree (Twig) | 4 wks | Thu 31-12-98 | Wed 27-01-99 | UAE Coordinator[50%],Physicist programmer 1[25%],Visualisation SW Engineer | 0% |
140 | CMSCAN display complete CMS detector | 2 wks | Thu 28-01-99 | Thu 11-02-99 | UAE Coordinator[50%],Visualisation SW Engineer | 0% |
141 | CMSCAN display of all ORCA reconstructed objects | 16 wks | Fri 12-02-99 | Fri 11-06-99 | UAE Coordinator[25%],Visualisation SW Engineer[50%] | 0% |
142 | CMSCAN development with ORCA | 23.8 wks | Fri 11-06-99 | Fri 10-12-99 | UAE Coordinator[0%],Visualisation SW Engineer[25%],UI/GUI SW Engineer 1[25%] | 0% |
143 | CMSCAN deployment for test beam | 12 wks | Mon 14-06-99 | Mon 13-09-99 | UAE Coordinator[25%],Visualisation SW Engineer[25%],UI/GUI SW Engineer 1[25%] | 0% |
144 | CMSCAN deployment for OSCAR | 12 wks | Tue 14-09-99 | Mon 13-12-99 | UAE Coordinator[25%],Visualisation SW Engineer[25%],UI/GUI SW Engineer 1[25%] | 0% |
145 | CMSCAN development (ORCA, test beam, OSCAR) | 23.6 wks | Tue 14-12-99 | Fri 09-06-00 | UAE Coordinator[25%],Visualisation SW Engineer[50%],UI/GUI SW Engineer 1[50%] | 0% |
146 | CMSCAN Functional Prototype (with ORCA) | 0 wks | Thu 15-06-00 | Thu 15-06-00 | 0% | |
147 | CMSCAN Development | 120 wks | Thu 15-06-00 | Fri 13-12-02 | 0% | |
148 | CMSCAN Development 1 | 120 wks | Thu 15-06-00 | Fri 13-12-02 | UAE Coordinator[25%],Visualisation SW Engineer[50%],UI/GUI SW Engineer 1[50%] | 0% |
149 | CMSCAN Fully Functional Software | 0 wks | Sat 14-12-02 | Sat 14-12-02 | 0% | |
150 | CMSCAN Productisation | 96 wks | Mon 16-12-02 | Tue 14-12-04 | 0% | |
151 | CMSCAN Productisation 1 | 96 wks | Mon 16-12-02 | Tue 14-12-04 | UAE Coordinator[25%],Visualisation SW Engineer[50%],UI/GUI SW Engineer 1[50%] | 0% |
152 | CMSCAN Production System | 0 wks | Wed 15-12-04 | Wed 15-12-04 | 0% | |
153 | CMSCAN Production | 99.8 wks | Wed 15-12-04 | Fri 29-12-06 | 0% | |
154 | CMSCAN Production 1 | 99.8 wks | Wed 15-12-04 | Fri 29-12-06 | UAE Coordinator[25%],Visualisation SW Engineer[50%],UI/GUI SW Engineer 1[50%] | 0% |
155 | Physics Analysis Tools | 393.61 wks | Mon 02-11-98 | Fri 29-12-06 | 0% | |
156 | PAT Development of concept | 6 wks | Mon 02-11-98 | Tue 15-12-98 | 0% | |
157 | Use of LHC++ tools with test-beam data | 6 wks | Mon 02-11-98 | Tue 15-12-98 | Test beam coordinator[0%] | 0% |
158 | PAT Functional protoyping | 58 wks | Wed 31-03-99 | Wed 14-06-00 | 0% | |
159 | PAT Functional Prototyping 1 | 58 wks | Wed 31-03-99 | Wed 14-06-00 | Visualisation SW Engineer[50%],UI/GUI SW Engineer 1[50%] | 0% |
160 | PAT Development | 120 wks | Wed 14-06-00 | Fri 13-12-02 | 0% | |
161 | PAT Development 1 | 120 wks | Wed 14-06-00 | Fri 13-12-02 | Visualisation SW Engineer[50%],Physics Analysis Tools SW Engineer,UI/GUI SW Engineer 1[50%] | 0% |
162 | PAT Productisation | 96 wks | Fri 13-12-02 | Tue 14-12-04 | 0% | |
163 | PAT Productisation 1 | 96 wks | Fri 13-12-02 | Tue 14-12-04 | Physics Analysis Tools SW Engineer,Visualisation SW Engineer[50%],UI/GUI SW Engineer 1[50%],UI/GUI SW Engineer 2 | 0% |
164 | PAT Production | 99.8 wks | Tue 14-12-04 | Fri 29-12-06 | 0% | |
165 | PAT Production 1 | 99.8 wks | Tue 14-12-04 | Fri 29-12-06 | Physics Analysis Tools SW Engineer,Visualisation SW Engineer[50%],UI/GUI SW Engineer 1[50%],UI/GUI SW Engineer 2 | 0% |
166 | UAE Proof of concept | 0 wks | Tue 15-12-98 | Tue 15-12-98 | 0% | |
167 | UAE Functional prototype | 0 wks | Thu 15-06-00 | Thu 15-06-00 | 0% | |
168 | UAE Fully functional software | 0 wks | Sun 15-12-02 | Sun 15-12-02 | 0% | |
169 | UAE Production software | 0 wks | Wed 15-12-04 | Wed 15-12-04 | 0% | |
170 | Testbeam | 433.8 wks | Thu 01-01-98 | Fri 29-12-06 | 0% | |
171 | Prototyping | 70 wks | Thu 01-01-98 | Mon 14-06-99 | Test beam coordinator[50%] | 0% |
172 | Functional prototype | 0 wks | Tue 15-06-99 | Tue 15-06-99 | 0% | |
173 | Development | 71.2 wks | Tue 15-06-99 | Fri 08-12-00 | Test beam coordinator[50%] | 0% |
174 | Fully functional software | 0 wks | Fri 15-12-00 | Fri 15-12-00 | 0% | |
175 | Productisation | 47 wks | Fri 15-12-00 | Fri 07-12-01 | Test beam coordinator[50%] | 0% |
176 | Production software | 0 wks | Fri 14-12-01 | Fri 14-12-01 | 0% | |
177 | Production, maintenance, and analysis | 244 wks | Fri 14-12-01 | Fri 29-12-06 | Test beam coordinator[50%] | 0% |
178 | Calibration | 289.8 wks | Mon 01-01-01 | Fri 29-12-06 | 0% | |
179 | Prototyping | 46 wks | Mon 01-01-01 | Fri 14-12-01 | Calibration coordinator[50%] | 0% |
180 | Functional prototype | 0 wks | Sat 15-12-01 | Sat 15-12-01 | 0% | |
181 | Development | 72 wks | Mon 17-12-01 | Fri 13-06-03 | Calibration coordinator | 0% |
182 | Fully functional software | 0 wks | Tue 17-06-03 | Tue 17-06-03 | 0% | |
183 | Productisation | 71.4 wks | Tue 17-06-03 | Fri 10-12-04 | Calibration coordinator,Calibration SW Engineer | 0% |
184 | Production software | 0 wks | Wed 15-12-04 | Wed 15-12-04 | 0% | |
185 | Production | 99.8 wks | Wed 15-12-04 | Fri 29-12-06 | Calibration coordinator,Calibration SW Engineer | 0% |
186 | ODBMS | 433.8 wks | Thu 01-01-98 | Fri 29-12-06 | 0% | |
187 | ODBMS for test beams | 433.8 wks | Thu 01-01-98 | Fri 29-12-06 | 0% | |
188 | Use of ODBMS for test beam data storage/retrieval | 0 wks | Thu 01-01-98 | Thu 01-01-98 | 0% | |
189 | ODBMS Test beam activities | 72 wks | Thu 01-01-98 | Wed 30-06-99 | Test beam coordinator[50%],DB Administrator 1[50%] | 0% |
190 | ODBMS Test beam data to MSS via ODBMS | 70 wks | Thu 01-07-99 | Thu 14-12-00 | Test beam coordinator[50%],DB Administrator 1[50%] | 0% |
191 | Integration of ODBMS and hierarchical MSS | 0 wks | Fri 15-12-00 | Fri 15-12-00 | 0% | |
192 | ODBMS Test beam production, maintenance, analysis | 291.8 wks | Fri 15-12-00 | Fri 29-12-06 | Test beam coordinator[50%],DB Administrator 1[50%] | 0% |
193 | ODBMS for event storage and retrieval | 433.8 wks | Thu 01-01-98 | Fri 29-12-06 | 0% | |
194 | ODBMS Event storage and retrieval development of concept | 22 wks | Thu 01-01-98 | Fri 12-06-98 | DB SW Engineer | 0% |
195 | ODBMS Event storage/retrieval: proof of concept | 0 wks | Mon 15-06-98 | Mon 15-06-98 | 0% | |
196 | ODBMS Event storage and retrieval prototyping | 71.6 wks | Mon 15-06-98 | Fri 10-12-99 | DB SW Engineer,DB Administrator 1[50%] | 0% |
197 | Functional prototype | 0 wks | Wed 15-12-99 | Wed 15-12-99 | 0% | |
198 | ODBMS Event storage and retrieval | 96 wks | Wed 15-12-99 | Fri 14-12-01 | DB SW Engineer,DB Administrator 1[50%] | 0% |
199 | Fully functional software | 0 wks | Mon 17-12-01 | Mon 17-12-01 | 0% | |
200 | ODBMS Event storage and retrieval | 96 wks | Mon 17-12-01 | Fri 12-12-03 | DB SW Chief Engineer,DB SW Engineer,DB Administrator 1[50%] | 0% |
201 | Production software | 0 wks | Mon 15-12-03 | Mon 15-12-03 | 0% | |
202 | ODBMS Event storage and production | 72 wks | Mon 15-12-03 | Tue 14-06-05 | DB SW Chief Engineer,DB SW Engineer,DB administrator 2,DB Administrator 1[50%] | 0% |
203 | ODBMS In production | 75.8 wks | Wed 15-06-05 | Fri 29-12-06 | DB SW Engineer,DB SW Chief Engineer,DB Administrator 1[50%],DB administrator 2 | 0% |
204 | ODBMS Evaluation | 433.4 wks | Mon 05-01-98 | Fri 29-12-06 | 0% | |
205 | Data organisation and access strategies | 45.4 wks | Mon 05-01-98 | Fri 11-12-98 | DB analyst | 0% |
206 | Data organisation and access strategy - proof of concept | 0 wks | Tue 15-12-98 | Tue 15-12-98 | 0% | |
207 | Tests of database performance | 23.8 wks | Tue 15-12-98 | Fri 11-06-99 | DB analyst | 0% |
208 | ODBMS filling with raw data at 100MB/s | 0 wks | Tue 15-06-99 | Tue 15-06-99 | 0% | |
209 | Measurements of distributed database performance | 72 wks | Tue 15-06-99 | Thu 14-12-00 | DB analyst | 0% |
210 | Simulation of distributed database performance | 96 wks | Tue 15-12-98 | Thu 14-12-00 | DB simulator/modeller | 0% |
211 | Simulation of data access patterns | 0 wks | Fri 15-12-00 | Fri 15-12-00 | 0% | |
212 | Final Evaluation of ODBMS and MSS | 48 wks | Fri 15-12-00 | Fri 14-12-01 | DB simulator/modeller,DB analyst | 0% |
213 | Choice of ODBMS vendor for running phase of CMS | 0 wks | Mon 17-12-01 | Mon 17-12-01 | 0% | |
214 | Commissioning of combined ODBMS and MSS system | 48 wks | Mon 17-12-01 | Fri 13-12-02 | DB simulator/modeller,DB analyst | 0% |
215 | Installation of production ODBMS software and MSS | 0 wks | Mon 16-12-02 | Mon 16-12-02 | 0% | |
216 | ODBMS Evaluation and tuning | 195.8 wks | Mon 16-12-02 | Fri 29-12-06 | DB simulator/modeller,DB analyst | 0% |
ID | Name | Group | Max Units | Peak Units |
---|---|---|---|---|
1 | 100% | 0% | ||
2 | PROJECT MANAGEMENT | 100% | 0% | |
3 | Project Manager | R.PM,T.PM,C.CE,F.CE_STAFF,I.CERN | 100% | 100% |
4 | Resource Manager | R.PM,T.PM,C.CE,F.CE_STAFF,I.CERN | 100% | 75% |
5 | Computing Manager | R.PM,T.PM,C.CE,F.CE_STAFF,I.CERN | 100% | 100% |
6 | 100% | 0% | ||
7 | COMPUTING | 100% | 0% | |
8 | Sys Admin 1 | R.SM,T.SYS_ADMIN,C.CE,F.CE_CMC,I.CERN | 100% | 0% |
9 | Sys Admin 2 | R.SM,T.SYS_ADMIN,C.NK,F.NK,I.NK | 0% | 0% |
10 | Sys Admin 3 | R.SM,T.SYS_ADMIN,C.NK,F.NK,I.NK | 0% | 0% |
11 | Sys Admin 4 | R.SM,T.SYS_ADMIN,C.NK,F.NK,I.NK | 0% | 0% |
12 | 100% | 0% | ||
13 | 100% | 0% | ||
14 | SOFTWARE | 100% | 0% | |
15 | 100% | 0% | ||
16 | CMSIM | 100% | 0% | |
17 | CMSIM Coordinator | R.PP,T.CMSIM,C.CE,F.CE_PA,I.CERN | 100% | 100% |
18 | 100% | 0% | ||
19 | Software Process | 100% | 0% | |
20 | SW Process Coordinator | R.SP,T.SW_PROCESS,C.CE_STAFF,F.CE,I.CERN | 100% | 100% |
21 | SW Process Toolsmith | R.SS,T.SW_PROCESS,C.NK,F.NK,I.NK | 0% | 100% |
22 | Quality Assurer | R.PP,T.SW_PROCESS,C.NK,F.NK,I.NK | 0% | 100% |
23 | 100% | 0% | ||
24 | SOFTWARE SUPPORT | 100% | 0% | |
25 | Librarian 1 | R.SS,T.SW_SUPPORT,C.FI,F.COMMON_PROJECT,I.CERN | 100% | 100% |
26 | Librarian 2 | R.SS,T.SW_SUPPORT,C.CE,F.NK,I.CERN | 0% | 100% |
27 | SS Toolsmith | R.SS,T.SW_SUPPORT,C.CE_FELLOW,F.CE,I.CERN | 50% | 100% |
28 | Documentor 1 | R.SS,T.SW_SUPPORT,C.NK,F.NK,I.NK | 0% | 100% |
29 | Documentor 2 | R.SS,T.SW_SUPPORT,C.NK,F.NK,I.NK | 0% | 100% |
30 | 100% | 0% | ||
31 | INFORMATION SYSTEMS | 100% | 0% | |
32 | WWW Coordinator | R.SS,T.INFO_SYSTEM,C.CE,F.CE_STAFF,I.CERN | 100% | 100% |
33 | WWW Administrator | R.SS,T.INFO_SYSTEM,C.CE,F.NK,I.CERN | 0% | 100% |
34 | Collaboration database programmer | R.SS,T.INFO_SYSTEM,C.CE,F.CE_STAFF,I.CERN | 0% | 50% |
35 | 100% | 0% | ||
36 | CARF | 100% | 0% | |
37 | Chief Architect | R.SA,T.CARF,C.CE,F.CE_STAFF,I.CERN | 100% | 100% |
38 | Architect | R.SA,T.CARF,C.NK,F.NK,I.NK | 0% | 100% |
39 | CARF SW Engineer | R.SA,T.CARF,C.NK,F.NK,I.NK | 0% | 100% |
40 | 100% | 0% | ||
41 | EVENT GENERATORS | 100% | 0% | |
42 | EG Coordinator | R.PP,T.EVT_GEN,C.NK,F.NK,I.NK | 0% | 100% |
43 | 100% | 0% | ||
44 | DETECTOR DESCRIPTION | 100% | 0% | |
45 | DD Coordinator | R.SP,T.DET_DESCRIPTION,C.CE,F.CE_STAFF,I.CERN | 100% | 100% |
46 | DD SW Engineer | R.SP,T.NK,C.CE,F.NK,I.CERN | 0% | 100% |
47 | Magnetic field programmer | R.PP,T.MAG_FIELD,C.FI,F.NK,I.HELSINKI | 100% | 25% |
48 | 100% | 0% | ||
49 | FAST SIMULATION | 100% | 0% | |
50 | Fast Sim. Coordinator | R.PP,T.NK,C.NK,F.NK,I.NK | 0% | 100% |
51 | Fast Sim. SW Engineer | R.SP,T.NK,C.NK,F.NK,I.NK | 0% | 100% |
52 | 100% | 0% | ||
53 | OSCAR | 100% | 0% | |
54 | OSCAR Coordinator | R.PP,T.OSCAR,C.CE,F.CE_STAFF,I.CERN | 100% | 100% |
55 | OSCAR SW Engineer | R.SP,T.CMSIM,C.CE,F.CE_FELLOW,I.CERN | 0% | 100% |
56 | Geometry coordinator | R.PP,T.NK,C.IN,F.NK,I.TIFR | 50% | 0% |
57 | Geometry programmer | R.PP,T.NK,C.NK,F.NK,I.NK | 100% | 0% |
58 | Programmer: Pixels | R.PP,T.NK,C.NK,F.NK,I.NK | 0% | 0% |
59 | Programmer: Silicon | R.PP,T.NK,C.NK,F.NK,I.NK | 0% | 0% |
60 | Programmer: MSGC | R.PP,T.NK,C.NK,F.NK,I.NK | 0% | 0% |
61 | Programmer: ECAL | R.PP,T.OSCAR,C.CH,F.NK,I.ETHZ | 0% | 0% |
62 | Programmer: HCAL | R.PP,T.NK,C.NK,F.NK,I.NK | 0% | 0% |
63 | Programmer: Muon barrel | R.PP,T.OSCAR,C.ES,F.NK,I.CANTABRIA | 100% | 0% |
64 | Programmer: EMU | R.PP,T.NK,C.NK,F.NK,I.NK | 0% | 0% |
65 | Programmer: Backgrounds | R.PP,T.NK,C.NK,F.NK,I.NK | 0% | 0% |
66 | 100% | 0% | ||
67 | ORCA | 100% | 0% | |
68 | ORCA Coordinator | R.PP,T.ORCA,C.US,F.US_DOE_BASE,I.PRINCETON | 100% | 100% |
69 | ORCA SW Engineer | R.SP,T.ORCA,C.US,F.US_DOE_PROJ,I.PRINCETON | 0% | 100% |
70 | Programmer: Tracker | R.PP,T.ORCA,C.CE,F.CE_PA,I.CERN | 100% | 100% |
71 | Programmer: Calorimetry | R.PP,T.ORCA,C.NK,F.NK,I.NK | 100% | 0% |
72 | Programmer: Muons | R.PP,T.ORCA,C.NK,F.NK,I.NK | 100% | 0% |
73 | Programmer: Trigger | R.PP,T.ORCA,C.NK,F.NK,I.NK | 100% | 0% |
74 | 100% | 0% | ||
75 | POR and HLT | 100% | 0% | |
76 | POR/HTL Coordinator | R.PP,T.POR_HLT,C.CE,F.CE_STAFF,I.CERN | 100% | 100% |
77 | POR/HLT SW Engineer | R.SP,T.POR_HLT,C.NK,F.NK,I.NK | 0% | 100% |
78 | 100% | 0% | ||
79 | USER ANALYSIS ENVIRONMENT | 100% | 0% | |
80 | UAE Coordinator | R.PP,T.UAE,C.US,F.US_NSF_BASE,I.NORTHEASTERN | 100% | 75% |
81 | Visualisation SW Engineer | R.SP,T.UAE,C.US,F.US_NSF_PROJ,I.NORTHEASTERN | 100% | 100% |
82 | UI/GUI SW Engineer 1 | R.SP,T.UAE,C.US,F.US_NSF_PROJ,I.NORTHEASTERN | 0% | 100% |
83 | UI/GUI SW Engineer 2 | R.SP,T.UAE,C.CE,F.NK,I.CERN | 0% | 100% |
84 | Physics Analysis Tools SW Engineer | R.SP,T.UAE,C.US,F.NK,I.NORTHEASTERN | 0% | 100% |
85 | Physicist programmer 1 | R.PP,T.UAE,C.US,F.US_NSF_BASE,I.NORTHEASTERN | 50% | 50% |
86 | Physicist programmer 2 | R.PP,T.UAE,C.US,F.US_NSF_BASE,I.NORTHEASTERN | 50% | 25% |
87 | 100% | 0% | ||
88 | TEST BEAM | 100% | 0% | |
89 | Test beam coordinator | R.SP,T.TEST_BEAM,C.CE,F.CE_PA,I.CERN | 100% | 100% |
90 | 100% | 0% | ||
91 | CALIBRATION | 100% | 0% | |
92 | Calibration coordinator | R.PP,T.CALIBRATION,C.NK,F.NK,I.NK | 100% | 100% |
93 | Calibration SW Engineer | R.SP,T.CALIBRATION,C.NK,F.NK,I.NK | 0% | 100% |
94 | 100% | 0% | ||
95 | ODBMS | 100% | 0% | |
96 | DB SW Chief Engineer | R.DP,T.ODBMS,C.CE,F.NK,I.CERN | 0% | 100% |
97 | DB SW Engineer | R.DP,T.ODBMS,C.CE,F.CE_CMC,I.CERN | 100% | 100% |
98 | DB Administrator 1 | R.DP,T.ODBMS,C.CE,F.NK,I.CERN | 100% | 100% |
99 | DB administrator 2 | R.DP,T.ODBMS,C.NK,F.NK,I.NK | 0% | 100% |
100 | DB simulator/modeller | R.DP,T.ODBMS,C.US,F.NK,I.NK | 0% | 100% |
101 | DB analyst | R.DP,T.ODBMS,C.US,F.NK,I.NK | 0% | 100% |
Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
---|---|---|---|---|---|---|
2 | Overall Project Management | Project Manager | 434 wks | Thu 01-01-98 | Mon 01-01-07 | 0% |
3 | Resource Management | Resource Manager | 325.5 wks | Thu 01-01-98 | Mon 01-01-07 | 0% |
4 | Computing co-ordination | Computing Manager | 434 wks | Thu 01-01-98 | Mon 01-01-07 | 0% |
24 | CMSIM development | CMSIM Coordinator | 22 wks | Thu 01-01-98 | Fri 12-06-98 | 0% |
26 | CMSIM maintenance | CMSIM Coordinator | 36 wks | Mon 15-06-98 | Thu 14-06-01 | 0% |
28 | SP Phase I: Development of proof of concept | SW Process Coordinator | 56 wks | Thu 01-01-98 | Fri 26-02-99 | 0% |
29 | SP Phase II: Development of functional prototype | SW Process Coordinator | 60 wks | Mon 01-03-99 | Fri 26-05-00 | 0% |
29 | SP Phase II: Development of functional prototype | Quality Assurer | 60 wks | Mon 01-03-99 | Fri 26-05-00 | 0% |
30 | SP Phase III: Development of fully functional software | SW Process Coordinator | 120 wks | Thu 01-06-00 | Thu 28-11-02 | 0% |
30 | SP Phase III: Development of fully functional software | SW Process Toolsmith | 120 wks | Thu 01-06-00 | Thu 28-11-02 | 0% |
30 | SP Phase III: Development of fully functional software | Quality Assurer | 120 wks | Thu 01-06-00 | Thu 28-11-02 | 0% |
31 | SP Phase IV: Development of production software | SW Process Coordinator | 197.8 wks | Mon 02-12-02 | Fri 29-12-06 | 0% |
31 | SP Phase IV: Development of production software | SW Process Toolsmith | 197.8 wks | Mon 02-12-02 | Fri 29-12-06 | 0% |
31 | SP Phase IV: Development of production software | Quality Assurer | 197.8 wks | Mon 02-12-02 | Fri 29-12-06 | 0% |
33 | SS Phase I: Development of proof of concept | Librarian 1 | 56 wks | Thu 01-01-98 | Fri 26-02-99 | 0% |
33 | SS Phase I: Development of proof of concept | SS Toolsmith | 56 wks | Thu 01-01-98 | Fri 26-02-99 | 0% |
33 | SS Phase I: Development of proof of concept | Documentor 1 | 56 wks | Thu 01-01-98 | Fri 26-02-99 | 0% |
34 | SS Phase II: Development of functional prototype | Librarian 1 | 60 wks | Mon 01-03-99 | Fri 26-05-00 | 0% |
34 | SS Phase II: Development of functional prototype | Documentor 1 | 60 wks | Mon 01-03-99 | Fri 26-05-00 | 0% |
34 | SS Phase II: Development of functional prototype | SS Toolsmith | 60 wks | Mon 01-03-99 | Fri 26-05-00 | 0% |
35 | SS Phase III: Development of fully functional software | Librarian 1 | 120 wks | Thu 01-06-00 | Thu 28-11-02 | 0% |
35 | SS Phase III: Development of fully functional software | Documentor 1 | 120 wks | Thu 01-06-00 | Thu 28-11-02 | 0% |
35 | SS Phase III: Development of fully functional software | SS Toolsmith | 120 wks | Thu 01-06-00 | Thu 28-11-02 | 0% |
36 | SS Phase IV: Development of production software | Librarian 1 | 197.8 wks | Mon 02-12-02 | Fri 29-12-06 | 0% |
36 | SS Phase IV: Development of production software | Documentor 1 | 197.8 wks | Mon 02-12-02 | Fri 29-12-06 | 0% |
36 | SS Phase IV: Development of production software | SS Toolsmith | 197.8 wks | Mon 02-12-02 | Fri 29-12-06 | 0% |
36 | SS Phase IV: Development of production software | Librarian 2 | 197.8 wks | Mon 02-12-02 | Fri 29-12-06 | 0% |
36 | SS Phase IV: Development of production software | Documentor 2 | 197.8 wks | Mon 02-12-02 | Fri 29-12-06 | 0% |
38 | WWW Phase 1 | WWW Coordinator | 239 wks | Thu 01-01-98 | Fri 20-12-02 | 0% |
39 | WWW Phase 2 | WWW Coordinator | 194.8 wks | Mon 23-12-02 | Fri 29-12-06 | 0% |
39 | WWW Phase 2 | WWW Administrator | 194.8 wks | Mon 23-12-02 | Fri 29-12-06 | 0% |
40 | Collaboration Database Phase 1 | Collaboration database programmer | 59.75 wks | Thu 01-01-98 | Fri 20-12-02 | 0% |
41 | Collaboration Database Phase 2 | Collaboration database programmer | 97.4 wks | Mon 23-12-02 | Fri 29-12-06 | 0% |
44 | CARF development of concept | Chief Architect | 22 wks | Thu 01-01-98 | Fri 12-06-98 | 0% |
47 | CARF prototyping 1 | Chief Architect | 71.4 wks | Tue 16-06-98 | Fri 10-12-99 | 0% |
47 | CARF prototyping 1 | Architect | 71.4 wks | Tue 16-06-98 | Fri 10-12-99 | 0% |
50 | CARF development 1 | Chief Architect | 92 wks | Mon 10-01-00 | Fri 07-12-01 | 0% |
50 | CARF development 1 | Architect | 92 wks | Mon 10-01-00 | Fri 07-12-01 | 0% |
53 | CARF productisation 1 | Chief Architect | 96 wks | Mon 17-12-01 | Fri 12-12-03 | 0% |
53 | CARF productisation 1 | Architect | 96 wks | Mon 17-12-01 | Fri 12-12-03 | 0% |
53 | CARF productisation 1 | CARF SW Engineer | 96 wks | Mon 17-12-01 | Fri 12-12-03 | 0% |
56 | CARF production 1 | Chief Architect | 148 wks | Tue 16-12-03 | Tue 02-01-07 | 0% |
56 | CARF production 1 | Architect | 148 wks | Tue 16-12-03 | Tue 02-01-07 | 0% |
56 | CARF production 1 | CARF SW Engineer | 148 wks | Tue 16-12-03 | Tue 02-01-07 | 0% |
58 | Implementation of Event Generator "Framework" | EG Coordinator | 25.6 wks | Tue 01-06-99 | Fri 10-12-99 | 0% |
60 | Maintenance of "Framework" | EG Coordinator | 68 wks | Wed 15-12-99 | Mon 01-01-07 | 0% |
61 | New generators, standard samples | EG Coordinator | 272 wks | Wed 15-12-99 | Mon 01-01-07 | 0% |
63 | Phase I | Magnetic field programmer | 11 wks | Mon 01-06-98 | Wed 28-04-99 | 0% |
64 | Phase II | Magnetic field programmer | 8 wks | Mon 03-05-99 | Sat 01-01-00 | 0% |
64 | Phase II | DD Coordinator | 16.01 wks | Mon 03-05-99 | Sat 01-01-00 | 0% |
64 | Phase II | DD SW Engineer | 32.01 wks | Mon 03-05-99 | Sat 01-01-00 | 0% |
65 | Phase III | Magnetic field programmer | 17.3 wks | Sat 01-01-00 | Fri 08-06-01 | 0% |
65 | Phase III | DD Coordinator | 69.19 wks | Sat 01-01-00 | Fri 08-06-01 | 0% |
65 | Phase III | DD SW Engineer | 69.19 wks | Sat 01-01-00 | Fri 08-06-01 | 0% |
66 | Phase IV | Magnetic field programmer | 67.15 wks | Mon 11-06-01 | Fri 29-12-06 | 0% |
66 | Phase IV | DD Coordinator | 268.6 wks | Mon 11-06-01 | Fri 29-12-06 | 0% |
66 | Phase IV | DD SW Engineer | 268.6 wks | Mon 11-06-01 | Fri 29-12-06 | 0% |
68 | Fast Sim: Development of concept | Fast Sim. Coordinator | 13 wks | Tue 01-06-99 | Tue 14-12-99 | 0% |
70 | Fast Sim: Development of functional prototype | Fast Sim. Coordinator | 48 wks | Wed 15-12-99 | Thu 14-12-00 | 0% |
70 | Fast Sim: Development of functional prototype | Fast Sim. SW Engineer | 48 wks | Wed 15-12-99 | Thu 14-12-00 | 0% |
72 | Fast Sim: Development of fully functional software | Fast Sim. Coordinator | 71 wks | Fri 15-12-00 | Fri 07-06-02 | 0% |
72 | Fast Sim: Development of fully functional software | Fast Sim. SW Engineer | 71 wks | Fri 15-12-00 | Fri 07-06-02 | 0% |
74 | Fast Sim: Development of production software | Fast Sim. Coordinator | 96 wks | Fri 14-06-02 | Fri 11-06-04 | 0% |
74 | Fast Sim: Development of production software | Fast Sim. SW Engineer | 96 wks | Fri 14-06-02 | Fri 11-06-04 | 0% |
76 | Fast Sim: production and development | Fast Sim. Coordinator | 123.8 wks | Tue 15-06-04 | Fri 29-12-06 | 0% |
76 | Fast Sim: production and development | Fast Sim. SW Engineer | 123.8 wks | Tue 15-06-04 | Fri 29-12-06 | 0% |
78 | OSCAR Development of concept | OSCAR Coordinator | 11 wks | Thu 01-01-98 | Fri 12-06-98 | 0% |
80 | OSCAR Prototyping | OSCAR Coordinator | 71.6 wks | Mon 15-06-98 | Fri 10-12-99 | 0% |
80 | OSCAR Prototyping | OSCAR SW Engineer | 71.6 wks | Mon 15-06-98 | Fri 10-12-99 | 0% |
82 | OSCAR Development | OSCAR Coordinator | 71.2 wks | Wed 15-12-99 | Fri 08-06-01 | 0% |
82 | OSCAR Development | OSCAR SW Engineer | 71.2 wks | Wed 15-12-99 | Fri 08-06-01 | 0% |
84 | OSCAR Production | OSCAR Coordinator | 120 wks | Fri 15-06-01 | Fri 12-12-03 | 0% |
84 | OSCAR Production | OSCAR SW Engineer | 120 wks | Fri 15-06-01 | Fri 12-12-03 | 0% |
86 | OSCAR Production | OSCAR Coordinator | 147.8 wks | Mon 15-12-03 | Fri 29-12-06 | 0% |
86 | OSCAR Production | OSCAR SW Engineer | 147.8 wks | Mon 15-12-03 | Fri 29-12-06 | 0% |
89 | Development of ORCA version 1 | Programmer: Tracker | 22 wks | Wed 01-07-98 | Mon 14-12-98 | 0% |
89 | Development of ORCA version 1 | ORCA Coordinator | 22 wks | Wed 01-07-98 | Mon 14-12-98 | 0% |
92 | Develop ORCA version 2 | ORCA Coordinator | 16 wks | Tue 15-12-98 | Wed 14-04-99 | 0% |
92 | Develop ORCA version 2 | Programmer: Tracker | 16 wks | Tue 15-12-98 | Wed 14-04-99 | 0% |
92 | Develop ORCA version 2 | ORCA SW Engineer | 16 wks | Tue 15-12-98 | Wed 14-04-99 | 0% |
94 | Develop ORCA version 3 | ORCA Coordinator | 16 wks | Thu 15-04-99 | Fri 13-08-99 | 0% |
94 | Develop ORCA version 3 | Programmer: Tracker | 16 wks | Thu 15-04-99 | Fri 13-08-99 | 0% |
94 | Develop ORCA version 3 | ORCA SW Engineer | 16 wks | Thu 15-04-99 | Fri 13-08-99 | 0% |
96 | Develop ORCA version 4 | ORCA Coordinator | 12 wks | Fri 20-08-99 | Thu 18-11-99 | 0% |
96 | Develop ORCA version 4 | Programmer: Tracker | 12 wks | Fri 20-08-99 | Thu 18-11-99 | 0% |
96 | Develop ORCA version 4 | ORCA SW Engineer | 12 wks | Fri 20-08-99 | Thu 18-11-99 | 0% |
100 | Development 1 | Programmer: Tracker | 120 wks | Wed 15-12-99 | Fri 14-06-02 | 0% |
100 | Development 1 | ORCA Coordinator | 120 wks | Wed 15-12-99 | Fri 14-06-02 | 0% |
100 | Development 1 | ORCA SW Engineer | 120 wks | Wed 15-12-99 | Fri 14-06-02 | 0% |
103 | Productisation 1 | Programmer: Tracker | 96 wks | Mon 17-06-02 | Mon 14-06-04 | 0% |
103 | Productisation 1 | ORCA Coordinator | 96 wks | Mon 17-06-02 | Mon 14-06-04 | 0% |
103 | Productisation 1 | ORCA SW Engineer | 96 wks | Mon 17-06-02 | Mon 14-06-04 | 0% |
106 | Production 1 | Programmer: Tracker | 124 wks | Tue 15-06-04 | Mon 01-01-07 | 0% |
106 | Production 1 | ORCA Coordinator | 124 wks | Tue 15-06-04 | Mon 01-01-07 | 0% |
106 | Production 1 | ORCA SW Engineer | 124 wks | Tue 15-06-04 | Mon 01-01-07 | 0% |
108 | POR_HLT Development of concept | POR/HTL Coordinator | 4.8 wks | Tue 05-01-99 | Fri 12-03-99 | 0% |
110 | POR_HLT Prototyping | POR/HTL Coordinator | 59.4 wks | Mon 15-03-99 | Fri 09-06-00 | 0% |
112 | POR_HLT Development | POR/HTL Coordinator | 120 wks | Thu 15-06-00 | Fri 13-12-02 | 0% |
112 | POR_HLT Development | POR/HLT SW Engineer | 120 wks | Thu 15-06-00 | Fri 13-12-02 | 0% |
114 | POR_HLT Production | POR/HTL Coordinator | 95.6 wks | Mon 16-12-02 | Fri 10-12-04 | 0% |
114 | POR_HLT Production | POR/HLT SW Engineer | 95.6 wks | Mon 16-12-02 | Fri 10-12-04 | 0% |
116 | POR_HLT Production | POR/HTL Coordinator | 99.8 wks | Wed 15-12-04 | Fri 29-12-06 | 0% |
116 | POR_HLT Production | POR/HLT SW Engineer | 99.8 wks | Wed 15-12-04 | Fri 29-12-06 | 0% |
119 | UAE Coordination 1 | UAE Coordinator | 9 wks | Thu 01-04-99 | Fri 31-12-99 | 0% |
120 | UAE Coordination 2 | UAE Coordinator | 59 wks | Sat 01-01-00 | Fri 14-06-02 | 0% |
121 | UAE Coordination 3 | UAE Coordinator | 110 wks | Mon 17-06-02 | Mon 01-01-07 | 0% |
125 | Standalone OpenGL/OpenInventor prototype | Physicist programmer 1 | 2 wks | Mon 05-01-98 | Tue 03-03-98 | 0% |
126 | Create basic SO classes and deploy HEPVis | Physicist programmer 1 | 2.5 wks | Wed 04-03-98 | Mon 18-05-98 | 0% |
127 | X11/MOTIF interactive GUI | UAE Coordinator | 3 wks | Wed 04-03-98 | Thu 16-04-98 | 0% |
127 | X11/MOTIF interactive GUI | Physicist programmer 1 | 1.5 wks | Wed 04-03-98 | Thu 16-04-98 | 0% |
128 | Interface with CMSIM (prototype display) | UAE Coordinator | 2 wks | Tue 19-05-98 | Tue 16-06-98 | 0% |
128 | Interface with CMSIM (prototype display) | Physicist programmer 1 | 1 wk | Tue 19-05-98 | Tue 16-06-98 | 0% |
129 | GEANT3 interface and SO classes for G3 shapes | UAE Coordinator | 3.3 wks | Wed 17-06-98 | Fri 07-08-98 | 0% |
129 | GEANT3 interface and SO classes for G3 shapes | Physicist programmer 1 | 1.65 wks | Wed 17-06-98 | Fri 07-08-98 | 0% |
129 | GEANT3 interface and SO classes for G3 shapes | Physicist programmer 2 | 1.65 wks | Wed 17-06-98 | Fri 07-08-98 | 0% |
132 | Integration with CARF, ORCA, SRT | UAE Coordinator | 3 wks | Mon 17-08-98 | Mon 28-09-98 | 0% |
133 | Display of some CMS detector elements | UAE Coordinator | 1 wk | Thu 01-10-98 | Wed 14-10-98 | 0% |
134 | Display of some ORCA reconstructed objects | UAE Coordinator | 1.5 wks | Thu 15-10-98 | Fri 06-11-98 | 0% |
135 | Integration and release with ORCA version 1 | UAE Coordinator | 1.5 wks | Mon 09-11-98 | Fri 27-11-98 | 0% |
138 | CMSCAN event display manager | UAE Coordinator | 1 wk | Mon 14-12-98 | Mon 28-12-98 | 0% |
138 | CMSCAN event display manager | Visualisation SW Engineer | 2 wks | Mon 14-12-98 | Mon 28-12-98 | 0% |
139 | CMSCAN management of graphics tree (Twig) | UAE Coordinator | 2 wks | Thu 31-12-98 | Wed 27-01-99 | 0% |
139 | CMSCAN management of graphics tree (Twig) | Physicist programmer 1 | 1 wk | Thu 31-12-98 | Wed 27-01-99 | 0% |
139 | CMSCAN management of graphics tree (Twig) | Visualisation SW Engineer | 4 wks | Thu 31-12-98 | Wed 27-01-99 | 0% |
140 | CMSCAN display complete CMS detector | UAE Coordinator | 1 wk | Thu 28-01-99 | Thu 11-02-99 | 0% |
140 | CMSCAN display complete CMS detector | Visualisation SW Engineer | 2 wks | Thu 28-01-99 | Thu 11-02-99 | 0% |
141 | CMSCAN display of all ORCA reconstructed objects | UAE Coordinator | 4 wks | Fri 12-02-99 | Fri 11-06-99 | 0% |
141 | CMSCAN display of all ORCA reconstructed objects | Visualisation SW Engineer | 8 wks | Fri 12-02-99 | Fri 11-06-99 | 0% |
142 | CMSCAN development with ORCA | UAE Coordinator | 0 wks | Fri 11-06-99 | Fri 11-06-99 | 0% |
142 | CMSCAN development with ORCA | Visualisation SW Engineer | 5.95 wks | Mon 14-06-99 | Fri 10-12-99 | 0% |
142 | CMSCAN development with ORCA | UI/GUI SW Engineer 1 | 5.95 wks | Mon 14-06-99 | Fri 10-12-99 | 0% |
143 | CMSCAN deployment for test beam | UAE Coordinator | 3 wks | Mon 14-06-99 | Mon 13-09-99 | 0% |
143 | CMSCAN deployment for test beam | Visualisation SW Engineer | 3 wks | Mon 14-06-99 | Mon 13-09-99 | 0% |
143 | CMSCAN deployment for test beam | UI/GUI SW Engineer 1 | 3 wks | Mon 14-06-99 | Mon 13-09-99 | 0% |
144 | CMSCAN deployment for OSCAR | UAE Coordinator | 3 wks | Tue 14-09-99 | Mon 13-12-99 | 0% |
144 | CMSCAN deployment for OSCAR | Visualisation SW Engineer | 3 wks | Tue 14-09-99 | Mon 13-12-99 | 0% |
144 | CMSCAN deployment for OSCAR | UI/GUI SW Engineer 1 | 3 wks | Tue 14-09-99 | Mon 13-12-99 | 0% |
145 | CMSCAN development (ORCA, test beam, OSCAR) | UAE Coordinator | 5.9 wks | Tue 14-12-99 | Fri 09-06-00 | 0% |
145 | CMSCAN development (ORCA, test beam, OSCAR) | Visualisation SW Engineer | 11.8 wks | Tue 14-12-99 | Fri 09-06-00 | 0% |
145 | CMSCAN development (ORCA, test beam, OSCAR) | UI/GUI SW Engineer 1 | 11.8 wks | Tue 14-12-99 | Fri 09-06-00 | 0% |
148 | CMSCAN Development 1 | UAE Coordinator | 30 wks | Thu 15-06-00 | Fri 13-12-02 | 0% |
148 | CMSCAN Development 1 | Visualisation SW Engineer | 60 wks | Thu 15-06-00 | Fri 13-12-02 | 0% |
148 | CMSCAN Development 1 | UI/GUI SW Engineer 1 | 60 wks | Thu 15-06-00 | Fri 13-12-02 | 0% |
151 | CMSCAN Productisation 1 | UAE Coordinator | 24 wks | Mon 16-12-02 | Tue 14-12-04 | 0% |
151 | CMSCAN Productisation 1 | Visualisation SW Engineer | 48 wks | Mon 16-12-02 | Tue 14-12-04 | 0% |
151 | CMSCAN Productisation 1 | UI/GUI SW Engineer 1 | 48 wks | Mon 16-12-02 | Tue 14-12-04 | 0% |
154 | CMSCAN Production 1 | UAE Coordinator | 24.95 wks | Wed 15-12-04 | Fri 29-12-06 | 0% |
154 | CMSCAN Production 1 | Visualisation SW Engineer | 49.9 wks | Wed 15-12-04 | Fri 29-12-06 | 0% |
154 | CMSCAN Production 1 | UI/GUI SW Engineer 1 | 49.9 wks | Wed 15-12-04 | Fri 29-12-06 | 0% |
157 | Use of LHC++ tools with test-beam data | Test beam coordinator | 0 wks | Mon 02-11-98 | Mon 02-11-98 | 0% |
159 | PAT Functional Prototyping 1 | Visualisation SW Engineer | 29 wks | Wed 31-03-99 | Wed 14-06-00 | 0% |
159 | PAT Functional Prototyping 1 | UI/GUI SW Engineer 1 | 29 wks | Wed 31-03-99 | Wed 14-06-00 | 0% |
161 | PAT Development 1 | Visualisation SW Engineer | 60 wks | Wed 14-06-00 | Fri 13-12-02 | 0% |
161 | PAT Development 1 | Physics Analysis Tools SW Engineer | 120 wks | Wed 14-06-00 | Fri 13-12-02 | 0% |
161 | PAT Development 1 | UI/GUI SW Engineer 1 | 60 wks | Wed 14-06-00 | Fri 13-12-02 | 0% |
163 | PAT Productisation 1 | Physics Analysis Tools SW Engineer | 96 wks | Fri 13-12-02 | Tue 14-12-04 | 0% |
163 | PAT Productisation 1 | Visualisation SW Engineer | 48 wks | Fri 13-12-02 | Tue 14-12-04 | 0% |
163 | PAT Productisation 1 | UI/GUI SW Engineer 1 | 48 wks | Fri 13-12-02 | Tue 14-12-04 | 0% |
163 | PAT Productisation 1 | UI/GUI SW Engineer 2 | 96 wks | Fri 13-12-02 | Tue 14-12-04 | 0% |
165 | PAT Production 1 | Physics Analysis Tools SW Engineer | 99.8 wks | Tue 14-12-04 | Fri 29-12-06 | 0% |
165 | PAT Production 1 | Visualisation SW Engineer | 49.9 wks | Tue 14-12-04 | Fri 29-12-06 | 0% |
165 | PAT Production 1 | UI/GUI SW Engineer 1 | 49.9 wks | Tue 14-12-04 | Fri 29-12-06 | 0% |
165 | PAT Production 1 | UI/GUI SW Engineer 2 | 99.8 wks | Tue 14-12-04 | Fri 29-12-06 | 0% |
171 | Prototyping | Test beam coordinator | 35 wks | Thu 01-01-98 | Mon 14-06-99 | 0% |
173 | Development | Test beam coordinator | 35.6 wks | Tue 15-06-99 | Fri 08-12-00 | 0% |
175 | Productisation | Test beam coordinator | 23.5 wks | Fri 15-12-00 | Fri 07-12-01 | 0% |
177 | Production, maintenance, and analysis | Test beam coordinator | 122 wks | Fri 14-12-01 | Fri 29-12-06 | 0% |
179 | Prototyping | Calibration coordinator | 23 wks | Mon 01-01-01 | Fri 14-12-01 | 0% |
181 | Development | Calibration coordinator | 72 wks | Mon 17-12-01 | Fri 13-06-03 | 0% |
183 | Productisation | Calibration coordinator | 71.4 wks | Tue 17-06-03 | Fri 10-12-04 | 0% |
183 | Productisation | Calibration SW Engineer | 71.4 wks | Tue 17-06-03 | Fri 10-12-04 | 0% |
185 | Production | Calibration coordinator | 99.8 wks | Wed 15-12-04 | Fri 29-12-06 | 0% |
185 | Production | Calibration SW Engineer | 99.8 wks | Wed 15-12-04 | Fri 29-12-06 | 0% |
189 | ODBMS Test beam activities | Test beam coordinator | 36 wks | Thu 01-01-98 | Wed 30-06-99 | 0% |
189 | ODBMS Test beam activities | DB Administrator 1 | 36 wks | Thu 01-01-98 | Wed 30-06-99 | 0% |
190 | ODBMS Test beam data to MSS via ODBMS | Test beam coordinator | 35 wks | Thu 01-07-99 | Thu 14-12-00 | 0% |
190 | ODBMS Test beam data to MSS via ODBMS | DB Administrator 1 | 35 wks | Thu 01-07-99 | Thu 14-12-00 | 0% |
192 | ODBMS Test beam production, maintenance, analysis | Test beam coordinator | 145.9 wks | Fri 15-12-00 | Fri 29-12-06 | 0% |
192 | ODBMS Test beam production, maintenance, analysis | DB Administrator 1 | 145.9 wks | Fri 15-12-00 | Fri 29-12-06 | 0% |
194 | ODBMS Event storage and retrieval development of concept | DB SW Engineer | 22 wks | Thu 01-01-98 | Fri 12-06-98 | 0% |
196 | ODBMS Event storage and retrieval prototyping | DB SW Engineer | 71.6 wks | Mon 15-06-98 | Fri 10-12-99 | 0% |
196 | ODBMS Event storage and retrieval prototyping | DB Administrator 1 | 35.8 wks | Mon 15-06-98 | Fri 10-12-99 | 0% |
198 | ODBMS Event storage and retrieval | DB SW Engineer | 96 wks | Wed 15-12-99 | Fri 14-12-01 | 0% |
198 | ODBMS Event storage and retrieval | DB Administrator 1 | 48 wks | Wed 15-12-99 | Fri 14-12-01 | 0% |
200 | ODBMS Event storage and retrieval | DB SW Chief Engineer | 96 wks | Mon 17-12-01 | Fri 12-12-03 | 0% |
200 | ODBMS Event storage and retrieval | DB SW Engineer | 96 wks | Mon 17-12-01 | Fri 12-12-03 | 0% |
200 | ODBMS Event storage and retrieval | DB Administrator 1 | 48 wks | Mon 17-12-01 | Fri 12-12-03 | 0% |
202 | ODBMS Event storage and production | DB SW Chief Engineer | 72 wks | Mon 15-12-03 | Tue 14-06-05 | 0% |
202 | ODBMS Event storage and production | DB SW Engineer | 72 wks | Mon 15-12-03 | Tue 14-06-05 | 0% |
202 | ODBMS Event storage and production | DB administrator 2 | 72 wks | Mon 15-12-03 | Tue 14-06-05 | 0% |
202 | ODBMS Event storage and production | DB Administrator 1 | 36 wks | Mon 15-12-03 | Tue 14-06-05 | 0% |
203 | ODBMS In production | DB SW Engineer | 75.8 wks | Wed 15-06-05 | Fri 29-12-06 | 0% |
203 | ODBMS In production | DB SW Chief Engineer | 75.8 wks | Wed 15-06-05 | Fri 29-12-06 | 0% |
203 | ODBMS In production | DB Administrator 1 | 37.9 wks | Wed 15-06-05 | Fri 29-12-06 | 0% |
203 | ODBMS In production | DB administrator 2 | 75.8 wks | Wed 15-06-05 | Fri 29-12-06 | 0% |
205 | Data organisation and access strategies | DB analyst | 45.4 wks | Mon 05-01-98 | Fri 11-12-98 | 0% |
207 | Tests of database performance | DB analyst | 23.8 wks | Tue 15-12-98 | Fri 11-06-99 | 0% |
209 | Measurements of distributed database performance | DB analyst | 72 wks | Tue 15-06-99 | Thu 14-12-00 | 0% |
210 | Simulation of distributed database performance | DB simulator/modeller | 96 wks | Tue 15-12-98 | Thu 14-12-00 | 0% |
212 | Final Evaluation of ODBMS and MSS | DB simulator/modeller | 48 wks | Fri 15-12-00 | Fri 14-12-01 | 0% |
212 | Final Evaluation of ODBMS and MSS | DB analyst | 48 wks | Fri 15-12-00 | Fri 14-12-01 | 0% |
214 | Commissioning of combined ODBMS and MSS system | DB simulator/modeller | 48 wks | Mon 17-12-01 | Fri 13-12-02 | 0% |
214 | Commissioning of combined ODBMS and MSS system | DB analyst | 48 wks | Mon 17-12-01 | Fri 13-12-02 | 0% |
216 | ODBMS Evaluation and tuning | DB simulator/modeller | 195.8 wks | Mon 16-12-02 | Fri 29-12-06 | 0% |
216 | ODBMS Evaluation and tuning | DB analyst | 195.8 wks | Mon 16-12-02 | Fri 29-12-06 | 0% |