Project Start Date: Thu 01-01-98
Project Finish Date: Fri 30-12-05
ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
---|---|---|---|---|---|---|
1 | USCMS Software and Computing | 2087 days | Thu 01-01-98 | Fri 30-12-05 | 0% | |
2 | Software | 2087 days | Thu 01-01-98 | Fri 30-12-05 | 2% | |
3 | ORCA | 2087 days | Thu 01-01-98 | Fri 30-12-05 | 0% | |
4 | IGUANA | 2087 days | Thu 01-01-98 | Fri 30-12-05 | 0% | |
5 | Distributed Data Analysis | 439 days | Sat 01-01-00 | Thu 06-09-01 | 17% | |
6 | Distributed Analysis | 374 days | Mon 03-04-00 | Thu 06-09-01 | 0% | |
7 | Distributed Task Scheduling | 60 days | Mon 03-04-00 | Fri 23-06-00 | 0% | |
8 | Initial Scheduling Service allowing clients to submit monitor and terminate jobs | 1 day | Mon 26-06-00 | Mon 26-06-00 | 0% | |
9 | Distributed Task Scheduling Development | 20 days | Tue 27-06-00 | Mon 24-07-00 | 0% | |
10 | Task scheduling test with ORCA and 32 processors | 1 day | Tue 25-07-00 | Tue 25-07-00 | 0% | |
11 | Redesign of task Scheduling to solve scalability problems | 40 days | Wed 26-07-00 | Tue 19-09-00 | 0% | |
12 | Test of New task scheduling design with 65 processors | 1 day | Wed 20-09-00 | Wed 20-09-00 | 0% | |
13 | Distributed Task Scheduling Development | 150 days | Thu 21-09-00 | Wed 18-04-01 | 0% | |
14 | Integration of Task Scheduler into GDMP prototype for distributed analysis | 1 day | Thu 19-04-01 | Thu 19-04-01 | 0% | |
15 | Fine Tuning Task Scheduler for Distributed Analysis and Production | 100 days | Fri 20-04-01 | Thu 06-09-01 | 0% | |
16 | Distributed Database Management | 414 days | Sat 01-01-00 | Thu 02-08-01 | 31% | |
17 | Perl Script Based Database Replication | 195 days | Sat 01-01-00 | Fri 29-09-00 | 95% | |
18 | Perl Script Database Replication Completed | 1 day | Mon 02-10-00 | Mon 02-10-00 | 0% | |
19 | GDMP Development | 125 days | Tue 01-02-00 | Mon 24-07-00 | 0% | |
20 | First Prototype presented | 1 day | Tue 25-07-00 | Tue 25-07-00 | 0% | |
21 | GDMP Development | 45 days | Wed 26-07-00 | Tue 26-09-00 | 0% | |
22 | Functional Prototype for Distributed Data Management | 1 day | Wed 27-09-00 | Wed 27-09-00 | 0% | |
23 | GDMP Development | 120 days | Thu 28-09-00 | Wed 14-03-01 | 0% | |
24 | Functional Prototype for Distributed Production | 1 day | Thu 15-03-01 | Thu 15-03-01 | 0% | |
25 | Converting Prototype into product for distributed Analysis | 100 days | Fri 16-03-01 | Thu 02-08-01 | 0% | |
26 | Distributed Production | 107 days | Thu 01-06-00 | Fri 27-10-00 | 0% | |
27 | First Large Scale Data Production at CERN | 15 days | Thu 01-06-00 | Wed 21-06-00 | 0% | |
28 | Creating of 1M muon and 1M jetmet events | 1 day | Thu 22-06-00 | Thu 22-06-00 | 0% | |
29 | Preparation of Remote Sites for Production | 70 days | Fri 23-06-00 | Thu 28-09-00 | 0% | |
30 | Installation of ORCA CMSIM Globus on Caltech Systems | 1 day | Mon 03-07-00 | Mon 03-07-00 | 0% | |
31 | Installation of ORCA CMSIM Globus on Wisconsin Condor Cluster | 1 day | Tue 01-08-00 | Tue 01-08-00 | 0% | |
32 | Production at Caltech and Wisconsin | 20 days | Fri 29-09-00 | Thu 26-10-00 | 0% | |
33 | Creation of 2 to 4 Million Events | 1 day | Fri 27-10-00 | Fri 27-10-00 | 0% | |
34 | Preparation of Software on Tier2 Prototype | 15 days | Mon 02-10-00 | Fri 20-10-00 | 0% | |
35 | Distributed System Simulation | 1715 days | Mon 02-11-98 | Fri 27-05-05 | 0% | |
36 | MONARC | 1715 days | Mon 02-11-98 | Fri 27-05-05 | 0% | |
37 | MONARC Development | 391 days | Mon 02-11-98 | Mon 01-05-00 | 0% | |
38 | Simulation of the CMS HLT Trigger Farm | 1 day | Tue 02-05-00 | Tue 02-05-00 | 0% | |
39 | MONARC Simulation | 21 days | Wed 03-05-00 | Wed 31-05-00 | 0% | |
40 | Simulation of Using Tapes for Specific HEP Applications | 1 day | Thu 01-06-00 | Thu 01-06-00 | 0% | |
41 | MONARC Simulation | 1300 days | Fri 02-06-00 | Thu 26-05-05 | 0% | |
42 | MONARC SIMULATIONS COMPLETE PROJECT FINISHED | 1 day | Fri 27-05-05 | Fri 27-05-05 | 0% | |
43 | Support | 2087 days | Thu 01-01-98 | Fri 30-12-05 | 0% | |
44 | Computing | 2087 days | Thu 01-01-98 | Fri 30-12-05 | 0% |
ID | Name | Group | Max Units | Peak Units |
---|
Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
---|